18905 W VANOWEN ST 91335

Certificate Information: 18905 W VANOWEN ST 91335

Application / Permit
19014-20000-06422
Plan Check / Job No.
B19VN20602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 2'-5" X 18'-2"ON 1ST FLOOR AND 36'-2" X 27'-5" IRREGULAR SHAPE 2ND FLOOR TO (E) RECREATION ROOM AND (E) CARPORT, AND CONVERT (E)REC.ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 PARISA ZAHABI
Corrections Issued 12/23/2019 PARISA ZAHABI
Green Plans Picked Up 1/7/2020 APPLICANT
Quality Review Completed 1/8/2020 OMID HEDAYAT
Building Plans Picked Up 1/13/2020 APPLICANT
Plan Check Approved 2/19/2020 PARISA ZAHABI
Issued 2/20/2020 LADBS
CofO in Progress 11/19/2020 VINCENT HANLEY
Permit Finaled 11/21/2020 DONALD SUNSERI
CofO Issued 11/21/2020 DONALD SUNSERI
Permit Finaled 11/21/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 1/13/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/13/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 2/6/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 2/11/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/11/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/11/2020 THOMAS LANG
ZI Cleared 2/12/2020 VINCENT QUITORIANO
Construction near power lines Cleared 2/20/2020 TORI CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Lampa,, Matthew Micheal; Lic. No.: C73161 4606 MARTSMITH WAY      FAIR OAKS, CA 95628

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/6/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 3/6/2020 Corrections Issued VINCENT HANLEY
Piling/Pier/Caisson 3/6/2020 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/12/2020 Partial Approval VINCENT HANLEY
Pre-Inspection 3/12/2020 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/20/2020 Approved VINCENT HANLEY
Piling/Pier/Caisson 3/20/2020 Approved VINCENT HANLEY
Pre-Inspection 5/14/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/10/2020 Not Ready for Inspection HENRY KIM
Green Building Rough 6/10/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 6/10/2020 Not Ready for Inspection HENRY KIM
Underground Mechanical 6/10/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 6/16/2020 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval DONALD SUNSERI
Wood Frame 6/16/2020 Partial Approval DONALD SUNSERI
BUILDING-Rough-Frame 6/26/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 6/26/2020 Approved VINCENT HANLEY
Green Building Rough 6/26/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 6/26/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 6/26/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/1/2020 Approved VINCENT HANLEY
Gas Test 7/1/2020 Partial Approval VINCENT HANLEY
Green Building Rough 7/1/2020 Approved VINCENT HANLEY
HVAC-Rough 7/1/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 7/1/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Not Ready VINCENT HANLEY
Wood Frame 7/1/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Corrections Issued VINCENT HANLEY
Insulation 7/20/2020 Approved VINCENT HANLEY
Shower Pan 7/20/2020 Approved VINCENT HANLEY
Drywall Nailing 7/24/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/29/2020 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 8/11/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/18/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 8/27/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 8/27/2020 Approved VINCENT HANLEY
Service/Power Release 8/27/2020 Not Ready for Inspection VINCENT HANLEY
Final 9/18/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 9/18/2020 Approved VINCENT HANLEY
Green Building Final 9/18/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/18/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/18/2020 Approved VINCENT HANLEY
Final 10/1/2020 Corrections Issued VINCENT HANLEY
Final 10/21/2020 Not Ready for Inspection RONALD COWAN
Final 11/19/2020 OK to Issue CofO VINCENT HANLEY
Service/Power Release 11/19/2020 Approved VINCENT HANLEY