7705 N MCLAREN AVE 91304

Certificate Information: 7705 N MCLAREN AVE 91304

Application / Permit
19014-20000-06407
Plan Check / Job No.
B19VN20542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add to and convert the detached garage into an irregular 21'x54' Accessory Dwelling Unit per AB 494 & SB 229
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 11/25/2019 ANGELICA DAVE
Corrections Issued 11/25/2019 ANGELICA DAVE
Plan Check Approved 2/24/2020 LUIS RINCON
Issued 2/24/2020 LADBS
CofO in Progress 11/9/2022 CHRIS CHRISTENSEN
Permit Finaled 11/18/2022 JOHN JANSON
CofO Issued 11/18/2022 JOHN JANSON
Permit Finaled 11/18/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/25/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/25/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/25/2019 GUILLERMO PETRA
Sewer availability Cleared 11/25/2019 GUILLERMO PETRA
Construction near power lines Cleared 2/22/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/21/2020 Not Ready for Inspection DAVID STEPANYAN
Pre-Inspection 1/26/2022 No Access for Inspection PETER FOLLING
Pre-Inspection 2/9/2022 Approved DAVID SCANTLIN
Underground Mechanical 6/16/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/23/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/30/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 8/3/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/3/2022 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 8/3/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/3/2022 Approved CHRIS CHRISTENSEN
Wood Frame 8/3/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/9/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/9/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/9/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/9/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 8/18/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/31/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/31/2022 Approved CHRIS CHRISTENSEN
Shower Pan 8/31/2022 Approved CHRIS CHRISTENSEN
Final 10/28/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/28/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/28/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/28/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/28/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/8/2022 Approved CHRIS CHRISTENSEN
Final 11/8/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/8/2022 Approved CHRIS CHRISTENSEN