10626 1/2 N SABLE AVE 91040
Certificate Information: 10626 1/2 N SABLE AVE 91040
- Application / Permit
- 19014-20000-06390
- Plan Check / Job No.
- B19VN20480
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14'-7" x 20'-10" ADDITION TO AND CONVERT THE DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA STD WFPP.
- Permit Issued
- Issued on 12/13/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2019 | ANGELICA DAVE |
| Corrections Issued | 11/22/2019 | ANGELICA DAVE |
| Plan Check Approved | 12/6/2019 | TROY DEGUZMAN |
| Issued | 12/13/2019 | LADBS |
| CofO in Progress | 10/20/2020 | JACK KARGODORIAN |
| CofO Issued | 11/2/2020 | MICHAEL SMITH |
| Permit Finaled | 11/2/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 12/4/2019 | DAVID FONSECA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/25/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/27/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 2/27/2020 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/27/2020 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/2/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/6/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 5/6/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/6/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/6/2020 | Approved | MATTHEW NELSON |
| Insulation | 7/21/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/29/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/29/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/4/2020 | Approved | MATTHEW NELSON |
| Shower Pan | 8/4/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | MATTHEW NELSON |
| Final | 9/25/2020 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/25/2020 | Approved | MATTHEW NELSON |
| Green Building Final | 9/25/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/25/2020 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 9/25/2020 | Approved | MATTHEW NELSON |