7047 W SHADYGROVE ST 91042
Certificate Information: 7047 W SHADYGROVE ST 91042
- Application / Permit
- 19014-20000-06384
- Plan Check / Job No.
- B19VN20471
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 17' X 25' IRR.-SHAPE PORTION OF (E) SINGLE FAMILY DWELLING AND 25' X 25' ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 11/25/2019 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 12/4/2019 | APPLICANT |
| Plan Check Approved | 3/11/2020 | GURUNATH NESARAJAH |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 10/8/2022 | DAVID ANDERSON |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 2/10/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/10/2020 | ADRIAN CASTRO |
| ZI | Cleared | 2/10/2020 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 3/3/2020 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 3/3/2020 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/12/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Drywall Nailing | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Final | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Final | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Final | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 11/15/2021 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 11/30/2021 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 1/18/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/3/2022 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 2/3/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 2/3/2022 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 2/3/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 2/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/23/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/23/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/23/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 2/23/2022 | Approved | MATTHEW NELSON |
| Insulation | 3/1/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 3/10/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 3/10/2022 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Not Ready | DAVID ANDERSON |
| ELECTRICAL-Final | 9/6/2022 | Corrections Issued | DAVID ANDERSON |
| HVAC-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/12/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 9/12/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/12/2022 | Approved | DAVID ANDERSON |
| Green Building Final | 9/12/2022 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 9/12/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 10/7/2022 | Approved | DAVID ANDERSON |
| Final | 10/7/2022 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 10/7/2022 | Approved | DAVID ANDERSON |