16055-16057 W ACRE ST 91343
Certificate Information: 16055-16057 W ACRE ST 91343
- Application / Permit
- 19014-20000-06383
- Plan Check / Job No.
- B19VN20462
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 20'3-1/2" X 37'10" 2ND FLOOR ADDITION OF ACCESSORY DWELLING UNIT TO (E) SFD AS PER AB 494 AND SB 229, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Green Plans Picked Up | 12/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | RARES BODEA |
| Corrections Issued | 12/9/2019 | RARES BODEA |
| Quality Review Completed | 12/12/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Applicant returned to address corrections | 2/19/2020 | RARES BODEA |
| Applicant returned to address corrections | 3/6/2020 | RARES BODEA |
| Plan Check Approved | 3/12/2020 | RARES BODEA |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 5/24/2022 | RAUL OLAGI |
| CofO Issued | 5/24/2022 | MICHAEL SMITH |
| Permit Finaled | 5/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/19/2020 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/24/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 3/3/2020 | SARAH YOUSSEF |
| Green Code | Cleared | 3/12/2020 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Monterrozo Construction Inc; Lic. No.: 1039434-B | P O BOX 16924 ENCINO, CA 91416 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/5/2020 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/6/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 5/6/2020 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 5/13/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 5/15/2020 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | CHARLES POWELL |
| Wood Frame | 5/22/2020 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/29/2020 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 6/29/2020 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 7/6/2020 | Approved | DANIEL DREW |
| HVAC-Rough | 7/6/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 7/6/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Approved | DANIEL DREW |
| Insulation | 7/17/2020 | Partial Approval | DANIEL DREW |
| Special/Order Compliance | 7/17/2020 | Approved | DANIEL DREW |
| Deputy Wood Construction | 8/4/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 8/24/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/24/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/28/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/17/2020 | Approved | DANIEL ORRANTE |
| Insulation | 9/28/2020 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 9/28/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/13/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/5/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/15/2021 | Approved | MICHEL ABAJAN |
| Service/Power Release | 7/16/2021 | Corrections Issued | JACK KARGODORIAN |
| Special/Order Compliance | 9/28/2021 | Approved | JACK KARGODORIAN |
| Final | 4/11/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/11/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 4/11/2022 | Approved | RAUL OLAGI |
| Final | 5/3/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Not Ready | RAUL OLAGI |
| Final | 5/23/2022 | OK to Issue CofO | RAUL OLAGI |
| HVAC-Final | 5/23/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 5/23/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Approved | RAUL OLAGI |