11313 N GOTHIC AVE 91344
Certificate Information: 11313 N GOTHIC AVE 91344
- Application / Permit
- 19014-20000-06376
- Plan Check / Job No.
- B19VN20427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 7' x 14' TO DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ANGELICA DAVE |
| Corrections Issued | 11/21/2019 | ANGELICA DAVE |
| Plan Check Approved | 11/25/2019 | ALDOUS CHIC |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 5/20/2021 | MARK JOHNSON |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 11/22/2019 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/22/2019 | TIMOTHY POWELL |
| Sewer availability | Cleared | 11/22/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/14/2020 | Partial Approval | ARAM AVEDISIAN |
| Pre-Inspection | 2/24/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 4/7/2020 | Partial Approval | MARK JOHNSON |
| Underground Mechanical | 4/7/2020 | Corrections Issued | MARK JOHNSON |
| Gas Test | 4/14/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 4/14/2020 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 4/14/2020 | Partial Approval | MARK JOHNSON |
| Underground Mechanical | 4/27/2020 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 5/11/2020 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 5/11/2020 | Not Ready for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 5/21/2020 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 5/22/2020 | Corrections Issued | CHARLES POWELL |
| ELECTRICAL-Rough | 5/27/2020 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 6/17/2020 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 6/22/2020 | Corrections Issued | DANIEL DREW |
| ELECTRICAL-Rough | 6/29/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/29/2020 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 7/6/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/6/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/10/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 7/10/2020 | Approved | MARK JOHNSON |
| Insulation | 7/10/2020 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 7/29/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 7/29/2020 | Not Ready for Inspection | MARK JOHNSON |
| Drywall Nailing | 8/12/2020 | Approved | MARK JOHNSON |
| Final | 12/14/2020 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 12/14/2020 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 12/14/2020 | Approved | MARK JOHNSON |
| Final | 12/24/2020 | Not Ready for Inspection | MARK JOHNSON |
| Final | 5/19/2021 | OK to Issue CofO | MARK JOHNSON |