10392 N ONEIDA AVE 91331

Certificate Information: 10392 N ONEIDA AVE 91331

Application / Permit
19014-20000-06367
Plan Check / Job No.
B19VN20406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DET. GARAGE W/ATT TRELLIS INTO ACCESSORY DWELLING UNIT W/ ADDN & W/ EX ATT TRELLIS PER AB 494 AND SB 229. SEE COMMENTS.
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 HAYATO TSUCHIYA
Corrections Issued 11/22/2019 HAYATO TSUCHIYA
Building Plans Picked Up 11/26/2019 APPLICANT
Plan Check Approved 2/21/2020 HAYATO TSUCHIYA
Issued 2/24/2020 LADBS
CofO in Progress 7/13/2020 MICHAEL SMITH
Permit Finaled 8/26/2020 MICHAEL SMITH
CofO Issued 8/26/2020 MICHAEL SMITH
Permit Finaled 8/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/12/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/12/2019 ADRIAN CASTRO
Sewer availability Cleared 12/12/2019 ADRIAN CASTRO
Construction near power lines Cleared 1/15/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/30/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2020 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 4/1/2020 No Access for Inspection MICHEL ABAJAN
Deputy Steel/Welding 4/1/2020 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 4/2/2020 Approved MICHEL ABAJAN
METHANE-Barrier 4/2/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 4/2/2020 Approved MICHEL ABAJAN
Underground Mechanical 4/2/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 4/28/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Partial Approval MICHEL ABAJAN
HVAC-Rough 4/28/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/28/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/7/2020 Approved MICHEL ABAJAN
Green Building Rough 5/7/2020 Approved MICHEL ABAJAN
Insulation 5/7/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/7/2020 Approved MICHEL ABAJAN
METHANE-Rough 5/7/2020 Approved MICHEL ABAJAN
Drywall Nailing 5/12/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/9/2020 Approved MICHEL ABAJAN
Final 7/9/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 7/9/2020 Approved MICHEL ABAJAN
HVAC-Final 7/9/2020 Approved MICHEL ABAJAN
PLUMBING-Final 7/9/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/9/2020 Approved MICHEL ABAJAN
Final 7/13/2020 OK to Issue CofO MICHEL ABAJAN