13195 W CHELTENHAM DR 91423

Certificate Information: 13195 W CHELTENHAM DR 91423

Application / Permit
19014-20000-06362
Plan Check / Job No.
B19VN20385
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING GARAGE TO LIVING AREA; NEW (2) CAR GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 SELLA BENYAMIN
Corrections Issued 11/22/2019 SELLA BENYAMIN
Building Plans Picked Up 11/25/2019 APPLICANT
Plan Check Approved 1/8/2020 SELLA BENYAMIN
Issued 1/8/2020 LADBS
CofO in Progress 6/12/2020 ARAM AVEDISIAN
Permit Finaled 8/22/2020 MICHAEL SMITH
CofO Issued 8/22/2020 MICHAEL SMITH
Permit Finaled 8/22/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/25/2019 JOSHUA DIAZ
Roof/Waste drainage to street Cleared 11/25/2019 JOSHUA DIAZ

Contact Information

Contractor S K A V Design Inc; Lic. No.: 288619-B 31858 CASTAIC ROAD STE 305      CASTAIC, CA 91384

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/13/2020 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 2/14/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 2/14/2020 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 2/21/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 2/21/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 2/21/2020 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 2/27/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 2/27/2020 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/4/2020 Partial Approval ARAM AVEDISIAN
Drywall Nailing 3/4/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/4/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 3/4/2020 Partial Approval ARAM AVEDISIAN
Insulation 3/11/2020 Approved JEFFREY PARD
Drywall Nailing 3/17/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/13/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 4/13/2020 Approved RAYMOND KEHOE
Drywall Nailing 4/15/2020 Approved JEFFREY PARD
Insulation 4/15/2020 Approved JEFFREY PARD
ELECTRICAL-Final 5/20/2020 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 5/20/2020 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 5/27/2020 Approved ARAM AVEDISIAN
Final 5/27/2020 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/27/2020 Approved ARAM AVEDISIAN
Green Building Final 5/27/2020 Approved ARAM AVEDISIAN
Green Building Rough 5/27/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/27/2020 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/27/2020 Approved ARAM AVEDISIAN
Final 6/12/2020 OK to Issue CofO ARAM AVEDISIAN