11069 W TIARA ST 91601

Certificate Information: 11069 W TIARA ST 91601

Application / Permit
19014-20000-06348
Plan Check / Job No.
B19VN20329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20' X 18'9" ADDITION & CONVERT 20' X 20' (E) DET. GARAGE TO (N) 20' X 38'9" ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEER.
Permit Issued
Issued on 2/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2019 APPLICANT
Assigned to Plan Check Engineer 11/20/2019 PINANK PATEL
Corrections Issued 11/20/2019 PINANK PATEL
Building Plans Picked Up 11/22/2019 APPLICANT
Plan Check Approved 2/3/2020 PINANK PATEL
Issued 2/3/2020 LADBS
CofO in Progress 10/23/2020 DANIEL DREW
CofO Issued 1/10/2022 MICHAEL SMITH
Permit Finaled 1/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 1/16/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/3/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Arsen, Adzhemyan; Lic. No.: C89103       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/13/2020 Approved RAYMOND KEHOE
Deputy Drilled-In Anchors 3/20/2020 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 3/20/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 4/1/2020 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 5/6/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 5/6/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval RAYMOND KEHOE
Green Building Rough 5/6/2020 Approved RAYMOND KEHOE
HVAC-Rough 5/6/2020 Corrections Issued RAYMOND KEHOE
Insulation 5/6/2020 Partial Approval RAYMOND KEHOE
PLUMBING-Rough 5/6/2020 Approved RAYMOND KEHOE
Insulation 6/3/2020 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 6/3/2020 Approved GREGG CUMMINGS
Drywall Nailing 7/3/2020 Approved MATTHEW NUCKOLLS
Insulation 7/3/2020 Approved MATTHEW NUCKOLLS
Service/Power Release 8/17/2020 Approved DANIEL DREW
Final 9/17/2020 Not Ready for Inspection DANIEL DREW
Green Building Final 9/17/2020 Not Ready for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Not Ready DANIEL DREW
Smoke Detectors 9/17/2020 Approved DANIEL DREW
Final 10/13/2020 Corrections Issued DANIEL DREW
Green Building Final 10/13/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Approved DANIEL DREW
Final 10/23/2020 OK to Issue CofO DANIEL DREW