4424 S CORINTH AVE 90230

Certificate Information: 4424 S CORINTH AVE 90230

Application / Permit
19014-20000-06337
Plan Check / Job No.
B19VN20302
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF (N) ACCESSORY DWELLING UNIT (20'-0"x 17'-9") ABOVE (E) GARAGE per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 MOHAMMAD ESMAILI
Corrections Issued 12/19/2019 MOHAMMAD ESMAILI
Green Plans Picked Up 12/19/2019 APPLICANT
Quality Review Completed 12/30/2019 OMID HEDAYAT
Building Plans Picked Up 1/2/2020 APPLICANT
Plan Check Approved 7/1/2021 MOHAMMAD ESMAILI
Issued 7/2/2021 APPLICANT
CofO in Progress 4/24/2023 RICHARD STEINBACH
Permit Finaled 4/24/2023 DANIEL ORRANTE
CofO Issued 4/24/2023 DANIEL ORRANTE
Permit Finaled 4/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/2/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 1/2/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/17/2020 JEANIE LAM
Sewer availability Cleared 1/17/2020 JEANIE LAM
Construction near power lines Cleared 2/8/2020 RIDWAN HARDY
Green Code Cleared 7/1/2021 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Ng,, Edward T W; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/19/2021 Approved KENNETH NAGLE
Deputy Drilled-In Anchors 10/20/2021 Approved ENRIQUE MIRELES
Wood Frame 11/9/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 9/12/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/19/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 9/30/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/30/2022 Approved JESUS RODRIGUEZ
Insulation 9/30/2022 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 9/30/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/5/2022 Partial Approval JESUS RODRIGUEZ
Green Building Rough 10/5/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/5/2022 Approved JESUS RODRIGUEZ
Shower Pan 10/5/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 10/24/2022 Approved JESUS RODRIGUEZ
Insulation 10/24/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/31/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 10/31/2022 Approved JESUS RODRIGUEZ
HVAC-Final 10/31/2022 Corrections Issued JESUS RODRIGUEZ
MERV13>=Rough 10/31/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/24/2023 Corrections Issued JESUS RODRIGUEZ
Final 2/24/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 2/24/2023 Approved JESUS RODRIGUEZ
HVAC-Final 2/24/2023 Corrections Issued JESUS RODRIGUEZ
MERV13>=Final 2/24/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 2/24/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 2/24/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/20/2023 Corrections Issued JESUS RODRIGUEZ
Final 4/20/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 4/20/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/21/2023 Approved JESUS RODRIGUEZ
Final 4/21/2023 Partial Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved JESUS RODRIGUEZ