4424 S CORINTH AVE 90230
Certificate Information: 4424 S CORINTH AVE 90230
- Application / Permit
- 19014-20000-06337
- Plan Check / Job No.
- B19VN20302
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF (N) ACCESSORY DWELLING UNIT (20'-0"x 17'-9") ABOVE (E) GARAGE per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | MOHAMMAD ESMAILI |
| Corrections Issued | 12/19/2019 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 12/19/2019 | APPLICANT |
| Quality Review Completed | 12/30/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 1/2/2020 | APPLICANT |
| Plan Check Approved | 7/1/2021 | MOHAMMAD ESMAILI |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 4/24/2023 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
| CofO Issued | 4/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/2/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/17/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 2/8/2020 | RIDWAN HARDY |
| Green Code | Cleared | 7/1/2021 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ng,, Edward T W; Lic. No.: C38552 | 979 E MUNCIE AVE FRESNO, CA 93720 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/19/2021 | Approved | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/9/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 9/12/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/19/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/30/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/30/2022 | Approved | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 9/30/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/5/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/24/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 10/24/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/31/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/31/2022 | Corrections Issued | JESUS RODRIGUEZ |
| MERV13>=Rough | 10/31/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 2/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 2/24/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| MERV13>=Final | 2/24/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/24/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 2/24/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 4/20/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/21/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/21/2023 | Partial Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | JESUS RODRIGUEZ |