6308 N COSTELLO AVE 91401
Certificate Information: 6308 N COSTELLO AVE 91401
- Application / Permit
- 19014-20000-06323
- Plan Check / Job No.
- B19VN20275
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REFRAME ENTIRE ROOF, CONVERT KITCHEN TO DINING ROOM AND ADD 24'7" X 36' TO THE REAR FOR RELOCATED KITCHEN, NEW BEDROOM, BATHROOM AND LAUNDRY CLOSET. ALL WORKS ARE PER DESIGN
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | ALDOUS CHIC |
| Corrections Issued | 12/2/2019 | ALDOUS CHIC |
| Quality Review Completed | 12/2/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 12/4/2019 | APPLICANT |
| Green Plans Picked Up | 12/4/2019 | APPLICANT |
| Plan Check Approved | 2/12/2020 | ALDOUS CHIC |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 5/19/2021 | MICHAEL TEMPLE |
| CofO Issued | 5/22/2021 | MICHAEL SMITH |
| Permit Finaled | 5/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/2/2020 | ALDOUS CHIC |
| Low Impact Development | Cleared | 1/31/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/26/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 4/7/2020 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/17/2020 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/1/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/5/2020 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/7/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/24/2020 | Corrections Issued | RAYMOND KEHOE |
| Footing/Foundation/Slab | 6/29/2020 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/28/2020 | Approved | WILLIAM KUEHN |
| Gas Test | 8/28/2020 | Partial Approval | WILLIAM KUEHN |
| HVAC-Rough | 8/28/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 8/28/2020 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 8/28/2020 | Approved | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 8/28/2020 | Approved | WILLIAM KUEHN |
| Insulation | 9/2/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 9/9/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/9/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | MICHAEL TEMPLE |
| Final | 5/12/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 5/12/2021 | Approved | MICHAEL TEMPLE |
| Green Building Final | 5/12/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 5/12/2021 | Approved | MICHAEL TEMPLE |
| Smoke Detectors | 5/12/2021 | Approved | MICHAEL TEMPLE |