6221 N TEESDALE AVE 91606

Certificate Information: 6221 N TEESDALE AVE 91606

Application / Permit
19014-20000-06279
Plan Check / Job No.
B19VN20077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO & CONVERT GARAGE TO A 2-STORY, TYPE VB, 20'-2"x33'-2" ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 SEAN SHAHMIRI
Corrections Issued 12/19/2019 SEAN SHAHMIRI
Quality Review Completed 12/23/2019 OMID HEDAYAT
Building Plans Picked Up 12/30/2019 APPLICANT
Green Plans Picked Up 12/30/2019 APPLICANT
Plan Check Approved 7/10/2020 SEAN SHAHMIRI
Applicant returned to address corrections 7/20/2020 SEAN SHAHMIRI
Issued 3/19/2021 APPLICANT
CofO in Progress 11/6/2023 KIRK SANDERS
Permit Finaled 1/17/2024 RUBEN SALAS
CofO Issued 1/17/2024 RUBEN SALAS
Permit Finaled 1/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/2/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/2/2020 THOMAS LANG
Construction near power lines Cleared 5/26/2020 WALTER RAMIREZ
Hydrant and Access approval Cleared 6/5/2020 MATTHEW CRAIG
Low Impact Development Cleared 6/26/2020 SARAH YOUSSEF
Sewer availability Cleared 6/26/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/29/2020 ADRIAN CASTRO
Green Code Cleared 7/1/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/26/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 6/7/2021 Approved RICHARD DOCKUS
Gas Test 6/15/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/20/2021 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 7/20/2021 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/28/2021 Partial Approval ADAM ESCOTO
PLUMBING-Rough 7/28/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 8/9/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/9/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/9/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/9/2021 Approved CHRISTOPHE COCHRAN
Insulation 8/13/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 8/24/2021 Approved MICHAEL PELHAM
Shower Pan 8/24/2021 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 9/7/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/5/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 11/5/2021 Approved CHRISTOPHE COCHRAN
Final 12/14/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 12/14/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/14/2022 Approved MICHEL ABAJAN
Final 4/11/2023 Partial Approval ROBERT GOLD
ELECTRICAL-Final 7/13/2023 Corrections Issued KIRK SANDERS
Final 11/2/2023 OK to Issue CofO KIRK SANDERS