13047 N DRONFIELD AVE 91342

Certificate Information: 13047 N DRONFIELD AVE 91342

Application / Permit
19014-20000-06268
Plan Check / Job No.
B19VN20027
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 10' X 13'-6" BREEZEWAY BETWEEN SFD AND GARAGE & STORAGE TO CREATE DETACHED GARAGE. CONVERT 20' X 28' DETACHED GARAGE & STORAGE AND ADD 6' X 9' TO CREATE (N) ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2019 APPLICANT
Assigned to Plan Check Engineer 11/18/2019 RAPHAEL ROSAS
Corrections Issued 11/18/2019 RAPHAEL ROSAS
Building Plans Picked Up 11/20/2019 APPLICANT
Issued 3/16/2020 LADBS
CofO in Progress 5/19/2022 JOHN HAYES
CofO Issued 6/1/2022 MICHAEL SMITH
Permit Finaled 6/1/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/20/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 11/20/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 11/21/2019 ELENA LOPEZ
ZA Case Cleared 11/21/2019 ANNA VAN
Sewer availability Cleared 12/2/2019 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/17/2020 Approved TROY SANDERS
PLUMBING-Rough 4/1/2020 Partial Approval TROY SANDERS
Shower Pan 4/1/2020 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 4/16/2020 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 4/16/2020 Partial Approval TROY SANDERS
Green Building Rough 4/16/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 4/16/2020 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/28/2020 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 8/10/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/10/2020 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/10/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/21/2020 Partial Approval MISAEL ESPARZA
Wood Frame 12/22/2020 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 2/10/2021 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/12/2021 Not Ready for Inspection BEAU COLLINS
Footing/Foundation/Slab 3/5/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 4/22/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 5/25/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/21/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/21/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/12/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 11/12/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/12/2021 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 12/14/2021 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/16/2021 Approved JOHN HAYES
Green Building Rough 12/16/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 12/16/2021 Approved JOHN HAYES
Insulation 12/21/2021 Approved JOHN HAYES
Drywall Nailing 1/3/2022 Approved MICHEL ABAJAN
Drywall Nailing 1/4/2022 Not Ready for Inspection JOHN HAYES
Final 2/11/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/11/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 2/11/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 2/11/2022 Not Ready for Inspection JOHN HAYES
Final 4/14/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/14/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 4/14/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/14/2022 Not Ready for Inspection JOHN HAYES
Final 4/21/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/21/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 4/21/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/21/2022 Not Ready for Inspection JOHN HAYES
Final 5/18/2022 OK to Issue CofO JOHN HAYES
Footing/Foundation/Slab 5/18/2022 Approved JOHN HAYES
Green Building Final 5/18/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved JOHN HAYES
Smoke Detectors 5/18/2022 Approved JOHN HAYES