12015 W ROSCOE BLVD 91352

Certificate Information: 12015 W ROSCOE BLVD 91352

Application / Permit
19014-20000-06232
Plan Check / Job No.
B19VN19933
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD19.5' x 15'4" TO DETACHED GARAGE AND CONVERTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 1/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 11/15/2019 ALDOUS CHIC
Corrections Issued 11/15/2019 ALDOUS CHIC
Plan Check Approved 1/21/2020 LUIS RINCON
Issued 1/22/2020 LADBS
CofO in Progress 2/23/2021 JOHN HAYES
CofO Issued 4/27/2021 MICHAEL SMITH
Permit Finaled 4/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/15/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/15/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/15/2019 ADRIAN CASTRO
Sewer availability Cleared 11/15/2019 ADRIAN CASTRO
Construction near power lines Cleared 1/15/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 2/13/2020 Corrections Issued JOHN HAYES
Pre-Inspection 2/13/2020 Not Ready for Inspection JOHN HAYES
Sewer 2/13/2020 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/31/2020 No Access for Inspection JOHN HAYES
PLUMBING-Rough 3/31/2020 No Access for Inspection JOHN HAYES
Deputy Drilled-In Anchors 4/21/2020 Partial Approval PIERRE VEGA
Excavation/Setback/Form/Re-Bar 4/22/2020 No Access for Inspection JOHN HAYES
PLUMBING-Rough 4/22/2020 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/27/2020 No Access for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/29/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/29/2020 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/7/2020 Approved JOHN HAYES
PLUMBING-Rough 5/7/2020 Partial Approval JOHN HAYES
Footing/Foundation/Slab 5/18/2020 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval ROBERT MINASSIANS
PLUMBING-Rough 6/16/2020 Corrections Issued ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 6/16/2020 SGSOV Not Ready ROBERT MINASSIANS
BUILDING-Rough-Frame 7/8/2020 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 7/8/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 No Access for Inspection PIERRE VEGA
Rough-Elec/Plmb/HVAC 8/17/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 9/2/2020 Corrections Issued MATTHEW NELSON
HVAC-Rough 9/2/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 9/2/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/15/2020 Partial Approval DAVID MATSON
HVAC-Rough 9/15/2020 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Approved DAVID MATSON
Insulation 9/22/2020 Approved DAVID MATSON
Interior/Exterior Lathing 9/29/2020 Not Ready for Inspection JOHN HAYES
Shower Pan 9/29/2020 Approved JOHN HAYES
Interior/Exterior Lathing 10/7/2020 Partial Approval JOHN HAYES
Drywall Nailing 10/14/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/14/2020 Not Ready for Inspection JOHN HAYES
Drywall Nailing 10/23/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/23/2020 Not Ready for Inspection JOHN HAYES
Drywall Nailing 10/28/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/28/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Not Ready JOHN HAYES
Drywall Nailing 11/2/2020 Approved JOHN HAYES
Green Building Rough 11/2/2020 Approved JOHN HAYES
PLUMBING-Final 11/2/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 1/12/2021 Not Ready for Inspection JOHN HAYES
Final 1/12/2021 Corrections Issued JOHN HAYES
Green Building Final 1/12/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/12/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/12/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/27/2021 Not Ready for Inspection JOHN HAYES
Final 1/27/2021 Corrections Issued JOHN HAYES
Green Building Final 1/27/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/27/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/22/2021 Approved JOHN HAYES
Final 2/22/2021 OK to Issue CofO JOHN HAYES
Green Building Final 2/22/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Approved JOHN HAYES
Smoke Detectors 2/22/2021 Approved JOHN HAYES