10359 W MARGATE ST 91601
Certificate Information: 10359 W MARGATE ST 91601
- Application / Permit
- 19014-20000-06220
- Plan Check / Job No.
- B19VN19904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" X 20'-0" DETACHED GARAGE AND ADD 11'-9" X 13'-11" AND 8'-5" X 13'-11" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP. SEE COMMENTS.
- Permit Issued
- Issued on 6/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2019 | JENNIFER LEE |
| Corrections Issued | 11/19/2019 | JENNIFER LEE |
| Plan Check Approved | 3/4/2020 | JEROME MAGAT PALMA |
| Issued | 6/9/2020 | LADBS |
| CofO in Progress | 6/28/2021 | ARAM AVEDISIAN |
| Permit Finaled | 5/27/2022 | MICHAEL SMITH |
| CofO Issued | 5/27/2022 | MICHAEL SMITH |
| Permit Finaled | 5/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 2/26/2020 | ERNEST FRESQUEZ |
| Construction within easement | Cleared | 2/26/2020 | ERNEST FRESQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/4/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 9/22/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 12/1/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/1/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/9/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Partial Approval | DANIEL DREW |
| Green Building Rough | 12/9/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 1/20/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 1/20/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 1/20/2021 | Approved | DANIEL DREW |
| Insulation | 1/26/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 1/26/2021 | Approved | DANIEL DREW |
| Sewer | 1/26/2021 | Approved | DANIEL DREW |
| Shower Pan | 1/26/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 2/5/2021 | Approved | DANIEL DREW |
| Green Building Rough | 2/5/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | ARAM AVEDISIAN |
| Final | 6/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 6/18/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 6/18/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 6/18/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/28/2021 | Approved | ARAM AVEDISIAN |
| Final | 6/28/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 6/28/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 6/28/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | ARAM AVEDISIAN |