10361 W MARGATE ST 91601

Certificate Information: 10361 W MARGATE ST 91601

Application / Permit
19014-20000-06213
Plan Check / Job No.
B19VN19887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 16'-11" X 30'-3" TO EXPAND AND REMODEL (E) BEDROOMS/BATHROOMS FOR AN (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 JEFFREY TANGONAN
Corrections Issued 11/15/2019 JEFFREY TANGONAN
Applicant returned to address corrections 3/18/2020 LUIS RINCON
Applicant returned to address corrections 4/24/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 5/26/2020 JENNIFER LEE
Issued 6/9/2020 LADBS
CofO in Progress 11/5/2021 DANIEL DREW
CofO Issued 5/27/2022 MICHAEL SMITH
Permit Finaled 5/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/4/2020 LEE GUILBEAUX
Sewer availability Cleared 3/4/2020 LEE GUILBEAUX
Low Impact Development Cleared 3/12/2020 MITESH PATEL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 10/16/2020 Partial Approval DANIEL DREW
Insulation 10/16/2020 Partial Approval DANIEL DREW
PLUMBING-Rough 10/16/2020 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/1/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/9/2020 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Partial Approval DANIEL DREW
Green Building Rough 12/9/2020 Not Ready for Inspection DANIEL DREW
PLUMBING-Rough 12/9/2020 Corrections Issued DANIEL DREW
ELECTRICAL-Rough 1/20/2021 Approved DANIEL DREW
HVAC-Rough 1/20/2021 Approved DANIEL DREW
PLUMBING-Rough 1/20/2021 Approved DANIEL DREW
Insulation 1/26/2021 Approved DANIEL DREW
Interior/Exterior Lathing 1/26/2021 Approved DANIEL DREW
Sewer 1/26/2021 Approved DANIEL DREW
Drywall Nailing 2/5/2021 Approved DANIEL DREW
Green Building Rough 2/5/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 6/15/2021 Approved ARAM AVEDISIAN
Final 6/15/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 6/15/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/15/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 11/4/2021 Approved DANIEL DREW
Final 11/4/2021 OK to Issue CofO DANIEL DREW
HVAC-Final 11/4/2021 Approved DANIEL DREW
PLUMBING-Final 11/4/2021 Approved DANIEL DREW