1918 N ECHO PARK AVE 90026

Certificate Information: 1918 N ECHO PARK AVE 90026

Application / Permit
19014-20000-06209
Plan Check / Job No.
B19VN19872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 23'-6" X 24'-9" FOR NEW BEDROOMS/BATHROOMS AND EXTEND KITCHEN FOR (E) 1-STORY SFD W/ UNDERFLOOR CRAWLSPACE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 JENNIFER LEE
Green Plans Picked Up 12/3/2019 APPLICANT
Corrections Issued 12/4/2019 JENNIFER LEE
Quality Review Completed 12/5/2019 STEVEN KIM
Building Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 2/19/2021 JENNIFER LEE
Issued 2/23/2021 APPLICANT
CofO in Progress 7/7/2022 THOMAS LOGRASSO
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/7/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/7/2020 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 2/24/2020 JENNIFER LEE
Grading Pre-Inspection Cleared 2/24/2020 JENNIFER LEE
Green Code Cleared 3/12/2020 AARON COSTA
Low Impact Development Cleared 1/6/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/29/2021 ROSA SILVA

Contact Information

Contractor Sire Energy Construction; Lic. No.: 1027415-B 21054 SHERMAN WAY #325      CANOGA PARK, CA 91303
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 5/3/2021 Partial Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 5/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/2/2021 Corrections Issued ROBERT VORHIS
Footing/Foundation/Slab 6/2/2021 Not Ready for Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 6/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 6/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 6/22/2021 Corrections Issued ROBERT VORHIS
Footing/Foundation/Slab 6/22/2021 Not Ready for Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 6/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 6/30/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Corrections Issued THOMAS LOGRASSO
Insulation 7/22/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/22/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 7/29/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 7/29/2021 Partial Approval THOMAS LOGRASSO
Underground Mechanical 7/29/2021 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval THOMAS LOGRASSO
Insulation 8/2/2021 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Corrections Issued THOMAS LOGRASSO
Wood Frame 9/7/2021 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/23/2021 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 9/23/2021 Approved THOMAS LOGRASSO
HVAC-Rough 9/23/2021 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 9/23/2021 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 9/28/2021 Corrections Issued THOMAS LOGRASSO
Green Building Rough 9/28/2021 Approved THOMAS LOGRASSO
Insulation 10/1/2021 Approved THOMAS LOGRASSO
Drywall Nailing 10/14/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/14/2021 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/28/2021 Not Ready for Inspection RUBEN SALAS
Interior/Exterior Lathing 11/2/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/21/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 1/21/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Not Ready THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Not Ready THOMAS LOGRASSO
BUILDING-Rough-Frame 2/24/2022 Not Ready for Inspection RUBEN SALAS
Final 2/24/2022 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 2/24/2022 Not Ready for Inspection RUBEN SALAS
Green Building Final 2/24/2022 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 2/24/2022 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 3/2/2022 Approved THOMAS LOGRASSO
Final 3/2/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 3/2/2022 Approved THOMAS LOGRASSO
Green Building Final 3/2/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 3/2/2022 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 3/2/2022 Partial Inspection ADAM ESCOTO
Final 3/8/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 3/8/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 3/8/2022 Approved THOMAS LOGRASSO
Final 3/10/2022 Partial Approval THOMAS LOGRASSO
Green Building Final 3/10/2022 Approved THOMAS LOGRASSO
Final 7/6/2022 OK to Issue CofO THOMAS LOGRASSO