5330 N LENNOX AVE 91401

Certificate Information: 5330 N LENNOX AVE 91401

Application / Permit
19014-20000-06207
Plan Check / Job No.
B19VN19871
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING. REMOVE AND ALTER INTERIOR WALLS, CONVERT PORTION OF (E) DWELLING TO (N) ATTACHED GARAGE.
Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 SEAN SHAHMIRI
Corrections Issued 12/6/2019 SEAN SHAHMIRI
Green Plans Picked Up 12/18/2019 APPLICANT
Quality Review Completed 12/19/2019 OMID HEDAYAT
Building Plans Picked Up 12/20/2019 APPLICANT
Plan Check Approved 1/15/2020 SEAN SHAHMIRI
Issued 1/16/2020 LADBS
CofO in Progress 9/28/2020 WILLIAM KUEHN
CofO Issued 10/16/2020 MICHAEL SMITH
Permit Finaled 10/16/2020 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/10/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/13/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 1/14/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/14/2020 GABRIEL ROBLES
Sewer availability Cleared 1/14/2020 GABRIEL ROBLES
Green Code Cleared 1/15/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Structural, Af; Lic. No.: C89103 1010 RALEGH ST   107    GLENDALE, CA

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2020 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 2/27/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 3/17/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 3/18/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/19/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval MISAEL ESPARZA
HVAC-Rough 5/6/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/6/2020 Corrections Issued MISAEL ESPARZA
Gas Test 5/7/2020 Partial Approval MISAEL ESPARZA
HVAC-Rough 5/7/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 5/7/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/8/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/8/2020 Approved MISAEL ESPARZA
Green Building Rough 5/8/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/12/2020 Approved MISAEL ESPARZA
Green Building Rough 5/12/2020 Approved MISAEL ESPARZA
Insulation 5/12/2020 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 5/12/2020 Partial Approval MISAEL ESPARZA
Drywall Nailing 5/19/2020 Approved BEAU COLLINS
Shower Pan 6/2/2020 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/4/2020 Corrections Issued MISAEL ESPARZA
Shower Pan 6/4/2020 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/8/2020 Approved MISAEL ESPARZA
Shower Pan 6/8/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/11/2020 Approved WILLIAM KUEHN
PLUMBING-Final 8/11/2020 Approved WILLIAM KUEHN
Final 9/15/2020 Not Ready for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 9/15/2020 Approved WILLIAM KUEHN
Green Building Final 9/15/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 9/15/2020 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 9/15/2020 Approved WILLIAM KUEHN
Final 9/22/2020 Not Ready for Inspection WILLIAM KUEHN
Final 9/25/2020 OK to Issue CofO WILLIAM KUEHN
Service/Power Release 9/25/2020 Approved WILLIAM KUEHN