5308 N BEVIS AVE 91411

Certificate Information: 5308 N BEVIS AVE 91411

Application / Permit
19014-20000-06192
Plan Check / Job No.
B19VN19813
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10' X 18' ADDITION TO (E) GARAGE AND CONVERSION TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; ADD 4'-2" X 18 TRELLIS
Permit Issued
Issued on 1/7/2020
Issuing Office
Valley
Current Status
Issued on 1/7/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 SELLA BENYAMIN
Corrections Issued 11/26/2019 SELLA BENYAMIN
Quality Review Completed 11/26/2019 GUANG MIN TUNG
Building Plans Picked Up 12/2/2019 APPLICANT
Green Plans Picked Up 12/2/2019 APPLICANT
Applicant returned to address corrections 12/19/2019 SELLA BENYAMIN
Plan Check Approved 12/26/2019 SELLA BENYAMIN
Issued 1/7/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 1/6/2020 DAVID MATSON

Contact Information

Contractor Caruso'S Construction; Lic. No.: 946650-B 6168 ELBA PLACE      WOODLAND HILLS, CA 91367

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/18/2020 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/27/2020 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/19/2020 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 3/19/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/7/2020 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 4/7/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 4/7/2020 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 4/7/2020 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 5/11/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 5/11/2020 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 5/11/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 5/11/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/14/2020 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 5/14/2020 No Access for Inspection CHARLES POWELL
Green Building Rough 5/14/2020 No Access for Inspection CHARLES POWELL
Insulation 5/14/2020 No Access for Inspection CHARLES POWELL
ELECTRICAL-Rough 5/18/2020 Corrections Issued CHARLES POWELL
Insulation 5/18/2020 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 5/18/2020 Approved CHARLES POWELL
Wood Frame 5/18/2020 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 5/20/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/20/2020 Approved THOMAS FINNILA
Green Building Rough 5/20/2020 Approved THOMAS FINNILA
Insulation 5/20/2020 Approved THOMAS FINNILA
Drywall Nailing 5/27/2020 Approved THOMAS FINNILA