5308 N BEVIS AVE 91411
Certificate Information: 5308 N BEVIS AVE 91411
- Application / Permit
- 19014-20000-06192
- Plan Check / Job No.
- B19VN19813
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 10' X 18' ADDITION TO (E) GARAGE AND CONVERSION TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; ADD 4'-2" X 18 TRELLIS
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Valley
- Current Status
- Issued on 1/7/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | SELLA BENYAMIN |
| Corrections Issued | 11/26/2019 | SELLA BENYAMIN |
| Quality Review Completed | 11/26/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/2/2019 | APPLICANT |
| Green Plans Picked Up | 12/2/2019 | APPLICANT |
| Applicant returned to address corrections | 12/19/2019 | SELLA BENYAMIN |
| Plan Check Approved | 12/26/2019 | SELLA BENYAMIN |
| Issued | 1/7/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 1/6/2020 | DAVID MATSON |
Contact Information
| Contractor | Caruso'S Construction; Lic. No.: 946650-B | 6168 ELBA PLACE WOODLAND HILLS, CA 91367 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/18/2020 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/27/2020 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/19/2020 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/19/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/7/2020 | Corrections Issued | RONALD COWAN |
| ELECTRICAL-Rough | 4/7/2020 | Not Ready for Inspection | RONALD COWAN |
| Green Building Rough | 4/7/2020 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 4/7/2020 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 5/11/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/11/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/11/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/14/2020 | Corrections Issued | CHARLES POWELL |
| ELECTRICAL-Rough | 5/14/2020 | No Access for Inspection | CHARLES POWELL |
| Green Building Rough | 5/14/2020 | No Access for Inspection | CHARLES POWELL |
| Insulation | 5/14/2020 | No Access for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 5/18/2020 | Corrections Issued | CHARLES POWELL |
| Insulation | 5/18/2020 | Not Ready for Inspection | CHARLES POWELL |
| Special/Order Compliance | 5/18/2020 | Approved | CHARLES POWELL |
| Wood Frame | 5/18/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 5/20/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/20/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 5/20/2020 | Approved | THOMAS FINNILA |
| Insulation | 5/20/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 5/27/2020 | Approved | THOMAS FINNILA |