5225 N FULTON AVE 91401

Certificate Information: 5225 N FULTON AVE 91401

Application / Permit
19014-20000-06162
Plan Check / Job No.
B19VN19731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(2) STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING; MAJOR REMODEL; EQUPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 SELLA BENYAMIN
Green Plans Picked Up 11/21/2019 APPLICANT
Corrections Issued 11/26/2019 SELLA BENYAMIN
Quality Review Completed 11/27/2019 GUANG MIN TUNG
Building Plans Picked Up 12/2/2019 APPLICANT
Plan Check Approved 1/2/2020 SELLA BENYAMIN
Issued 1/8/2020 LADBS
TCO Issued (Expire Date: 03-19-2022) 9/20/2021 MICHAEL SMITH
CofO in Progress 11/5/2021 MICHAEL PELHAM
Permit Finaled 11/6/2021 MICHAEL SMITH
CofO Issued 11/6/2021 MICHAEL SMITH
Permit Finaled 11/6/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/16/2019 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 12/19/2019 GUILLERMO PETRA
Sewer availability Cleared 12/19/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 12/30/2019 JEREMY CARTER
Low Impact Development Cleared 12/30/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 1/2/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2020 Corrections Issued DAVID SANDOVAL
Sewer 4/24/2020 Approved RAYMOND KEHOE
Underground Mechanical 4/24/2020 Partial Approval RAYMOND KEHOE
Deputy Drilled-In Anchors 5/5/2020 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 5/11/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 5/12/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/8/2020 Corrections Issued CHARLES POWELL
Green Building Rough 6/8/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 6/11/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 6/11/2020 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/8/2020 Partial Approval BRENDAN LOONEY
Green Building Rough 7/8/2020 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 7/17/2020 Conditional Approval DANIEL ORRANTE
BUILDING-Rough-Frame 8/4/2020 Partial Inspection DANIEL ORRANTE
Green Building Rough 8/4/2020 Not Ready for Inspection DANIEL ORRANTE
Pre-Inspection 8/18/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 10/16/2020 Corrections Issued CHARLES POWELL
Underground Mechanical 10/16/2020 Approved CHARLES POWELL
HVAC-Rough 11/4/2020 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 11/4/2020 Approved CHARLES POWELL
Deputy Wood Construction 11/12/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 12/2/2020 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/31/2020 Corrections Issued THOMAS FINNILA
HVAC-Rough 12/31/2020 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 1/5/2021 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 1/5/2021 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/6/2021 Corrections Issued CHARLES POWELL
Green Building Rough 1/6/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 1/20/2021 Partial Approval CHARLES POWELL
Green Building Rough 1/20/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 1/20/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 1/25/2021 Conditional Approval THOMAS FINNILA
Insulation 1/25/2021 Partial Approval THOMAS FINNILA
Drywall Nailing 2/11/2021 Approved ARAM AVEDISIAN
Pre-Inspection 2/25/2021 Partial Inspection ARAM AVEDISIAN
Shower Pan 4/7/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 5/7/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 5/19/2021 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 5/24/2021 Approved CHARLES POWELL
Final 6/2/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 6/2/2021 Not Ready for Inspection JOHN HAYES
Pre-Inspection 6/16/2021 Not Ready for Inspection CHARLES POWELL
Grading Pre-Inspection 6/24/2021 Partial Inspection CHARLES POWELL
Pre-Inspection 7/22/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 8/6/2021 Approved CHARLES POWELL
Final 8/6/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 8/6/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 8/6/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 8/6/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Final 8/10/2021 Corrections Issued CHARLES POWELL
ELECTRICAL-Final 8/11/2021 Not Ready for Inspection CHARLES POWELL
Gas Test 8/23/2021 Approved CHARLES POWELL
Green Building Final 8/23/2021 Approved CHARLES POWELL
HVAC-Final 8/23/2021 Partial Approval CHARLES POWELL
PLUMBING-Final 8/23/2021 Partial Approval CHARLES POWELL
Final 8/30/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 8/30/2021 Approved CHARLES POWELL
ELECTRICAL-Final 9/2/2021 Approved CHARLES POWELL
Final 9/2/2021 Corrections Issued CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved CHARLES POWELL
Service/Power Release 9/2/2021 Partial Approval CHARLES POWELL
Service/Power Release 9/20/2021 Approved MICHAEL PELHAM
Final 11/5/2021 OK to Issue CofO MICHAEL PELHAM