20330 W LASSEN ST 91311

Certificate Information: 20330 W LASSEN ST 91311

Application / Permit
19014-20000-06155
Plan Check / Job No.
B19VN19700
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION (22'-8"x33'-0") TO (E) 1 STORY SFD
Permit Issued
Issued on 9/25/2020
Issuing Office
Current Status
CofO Issued on 9/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 MOHAMMAD ESMAILI
Corrections Issued 12/10/2019 MOHAMMAD ESMAILI
Quality Review Completed 12/18/2019 OMID HEDAYAT
Building Plans Picked Up 12/18/2019 APPLICANT
Green Plans Picked Up 12/18/2019 APPLICANT
Applicant returned to address corrections 2/7/2020 MOHAMMAD ESMAILI
Plan Check Approved 2/19/2020 MOHAMMAD ESMAILI
Issued 9/25/2020 APPLICANT
CofO in Progress 9/1/2021 JEFFREY PARD
CofO Issued 9/1/2021 JOHN JANSON
Permit Finaled 9/1/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/16/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/16/2020 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 1/23/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/23/2020 ERIK BEASLEY
Green Code Cleared 1/28/2020 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/18/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval JEFFREY PARD
HVAC-Rough 2/3/2021 Approved JEFFREY PARD
Wood Frame 2/3/2021 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 2/11/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/11/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/11/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/17/2021 Approved JEFFREY PARD
PLUMBING-Rough 2/17/2021 Approved JEFFREY PARD
Wood Frame 2/17/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/22/2021 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 3/10/2021 Approved JEFFREY PARD
Insulation 3/22/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/30/2021 Approved JEFFREY PARD
Gas Test 4/16/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 4/22/2021 Partial Approval JOSEPH SAGEN
Green Building Final 5/19/2021 Corrections Issued JEFFREY PARD
HVAC-Final 5/19/2021 Approved JEFFREY PARD
PLUMBING-Final 5/19/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 5/21/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 6/3/2021 Approved JEFFREY PARD
Final 6/3/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 6/3/2021 Approved JEFFREY PARD
Green Building Final 6/3/2021 Approved JEFFREY PARD
Green Building Rough 6/3/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 6/3/2021 Approved JEFFREY PARD
Final 8/31/2021 OK to Issue CofO JEFFREY PARD
PLUMBING-Final 8/31/2021 Approved JEFFREY PARD