19750 W SCHOOLCRAFT ST 91306
Certificate Information: 19750 W SCHOOLCRAFT ST 91306
- Application / Permit
- 19014-20000-06154
- Plan Check / Job No.
- B19VN19690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Irregular 15'6" x 25'3" ADDITION and ALTERATION to enlarge full master bathroom, create utility room, create half bathroom, relocate kitchen, and add a dining room.
- Permit Issued
- Issued on 11/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2019 | LUIS RINCON |
| Corrections Issued | 11/13/2019 | LUIS RINCON |
| Plan Check Approved | 11/15/2019 | HAYATO TSUCHIYA |
| Issued | 11/19/2019 | LADBS |
| CofO in Progress | 4/22/2020 | HENRY KIM |
| Permit Finaled | 4/23/2020 | DONALD SUNSERI |
| CofO Issued | 4/23/2020 | DONALD SUNSERI |
| Permit Finaled | 4/23/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 11/13/2019 | GUILLERMO PETRA |
| ZI | Cleared | 11/15/2019 | DAISY BENICIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2019 | Approved | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 12/19/2019 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 1/8/2020 | Partial Approval | HENRY KIM |
| Green Building Rough | 1/8/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2020 | Partial Approval | HENRY KIM |
| Insulation | 1/10/2020 | Partial Approval | HENRY KIM |
| Wood Frame | 1/28/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 2/6/2020 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 2/6/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 2/6/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2020 | Conditional Approval | HENRY KIM |
| Green Building Rough | 2/6/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 2/6/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 2/6/2020 | Approved | HENRY KIM |
| Green Building Rough | 2/19/2020 | Approved | HENRY KIM |
| Insulation | 2/19/2020 | Approved | HENRY KIM |
| Shower Pan | 2/19/2020 | Approved | HENRY KIM |
| Drywall Nailing | 2/24/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 2/27/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 4/22/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 4/22/2020 | Approved | HENRY KIM |
| Final | 4/22/2020 | OK to Issue CofO | HENRY KIM |
| Footing/Foundation/Slab | 4/22/2020 | Approved | HENRY KIM |
| Green Building Final | 4/22/2020 | Approved | HENRY KIM |
| HVAC-Final | 4/22/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 4/22/2020 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/22/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 4/22/2020 | Approved | HENRY KIM |