4247 S GRAND VIEW BLVD 90066

Certificate Information: 4247 S GRAND VIEW BLVD 90066

Application / Permit
19014-20000-06143
Plan Check / Job No.
B19VN19648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 22'10" X 13'10" ADDITION TO (E) SINGLE FAMILY DWELLING TO EXTEND LIVING ROOM AND ADD LAUNDRY ROOM, ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/22/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/12/2019 ROSENDO MEDINA
Corrections Issued 11/12/2019 ROSENDO MEDINA
Applicant returned to address corrections 11/19/2019 RARES BODEA
Issued 11/22/2019 LADBS
CofO in Progress 8/3/2020 JUAN VALENZUELA
Permit Finaled 9/8/2020 VINCENT COTTON
CofO Issued 9/8/2020 VINCENT COTTON
Permit Finaled 9/8/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/12/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 11/12/2019 APEKSHYA BAJRACHARYA
Public Works-Highway Ded. Cleared 11/12/2019 APEKSHYA BAJRACHARYA
Public Works-Open Permits Cleared 11/12/2019 APEKSHYA BAJRACHARYA
Public Works-Sewers Cleared 11/12/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/16/2019 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 12/17/2019 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 12/30/2019 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/3/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 1/21/2020 Corrections Issued DAVID FEILER
Green Building Rough 1/21/2020 Not Ready for Inspection DAVID FEILER
Insulation 1/31/2020 Partial Approval CRAIG DAVIS
Pre-Inspection 1/31/2020 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 2/5/2020 Partial Approval KEVIN BEAULIEU
ELECTRICAL-Rough 2/5/2020 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 2/5/2020 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 2/5/2020 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 2/11/2020 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval CRAIG DAVIS
Green Building Rough 2/11/2020 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/19/2020 Approved CRAIG DAVIS
ELECTRICAL-Rough 2/21/2020 Approved OGANES TARAKHCHYAN
Insulation 2/26/2020 Approved JUAN VALENZUELA
Drywall Nailing 3/2/2020 Approved DAVID HEINE
Green Building Rough 3/2/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 7/21/2020 Approved JOHNNY MIRANDA
Final 7/21/2020 Corrections Issued JOHNNY MIRANDA
Green Building Final 7/21/2020 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/21/2020 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/21/2020 Approved JOHNNY MIRANDA
Final 7/24/2020 Conditional Approval DAVID HEINE
Final 7/29/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 8/3/2020 Approved JUAN VALENZUELA
Final 8/3/2020 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 8/3/2020 Approved JUAN VALENZUELA
PLUMBING-Final 8/3/2020 Approved JUAN VALENZUELA