8521 N NEWCASTLE AVE 91325

Certificate Information: 8521 N NEWCASTLE AVE 91325

Application / Permit
19014-20000-06138
Plan Check / Job No.
B19VN19633
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) KICHEN TO FAMILY ROOM, CONVERT (E)BATH TO HALLWAY. CONVERT BREEZEWAY TO BATHROOM AND HALLWAY. ADD 23'-3" X 39'-0" IRREGULAR SHAPE 2 STORY LIVING ROOM W/ KICHECN ON 1ST FLOOR AND ONE FULL BATH W/ MASTER BEDROOM AND CLOSET ON 2ND FLOOR TO SFD. ALL WORK PER ENGINEERING. ***** SEE COMMENTS ****
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 PARISA ZAHABI
Green Plans Picked Up 12/10/2019 APPLICANT
Corrections Issued 12/12/2019 PARISA ZAHABI
Quality Review Completed 12/17/2019 OMID HEDAYAT
Building Plans Picked Up 12/17/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 PARISA ZAHABI
Applicant returned to address corrections 2/24/2020 PARISA ZAHABI
Plan Check Approved 9/4/2020 PARISA ZAHABI
Issued 10/14/2020 APPLICANT
CofO in Progress 4/29/2022 MICHAEL TEMPLE
CofO Issued 5/10/2022 MICHAEL SMITH
Permit Finaled 5/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 2/4/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 2/6/2020 AARON COSTA
Roof/Waste drainage to street Cleared 2/6/2020 ADRIAN CASTRO
Private sewage disp. approval Cleared 3/4/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/13/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 5/19/2021 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 5/20/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/10/2021 Not Ready for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Partial Approval MICHAEL TEMPLE
Deputy Steel/Welding 7/27/2021 No Access for Inspection MARK JOHNSON
BUILDING-Rough-Frame 8/4/2021 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/4/2021 Partial Approval MATTHEW NELSON
Green Building Rough 8/4/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 9/10/2021 Not Ready for Inspection MARK JOHNSON
Gas Test 9/10/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 9/10/2021 Not Ready for Inspection MARK JOHNSON
Rough-Elec/Plmb/HVAC 9/10/2021 Not Ready for Inspection MARK JOHNSON
Sewer 9/10/2021 Approved MARK JOHNSON
Structural Steel Frame 9/10/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 9/21/2021 Corrections Issued MARK JOHNSON
Deputy Wood Construction 9/21/2021 Approved MARK JOHNSON
Green Building Rough 9/21/2021 Not Ready for Inspection MARK JOHNSON
Rough-Elec/Plmb/HVAC 9/21/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/29/2021 Approved MARK JOHNSON
Green Building Rough 9/29/2021 Approved MARK JOHNSON
HVAC-Rough 9/29/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 9/29/2021 Approved MARK JOHNSON
Insulation 10/18/2021 Approved MARK JOHNSON
Drywall Nailing 11/12/2021 Approved JESUS RODRIGUEZ
Shower Pan 11/23/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/30/2021 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/10/2022 Corrections Issued RAUL OLAGI
Final 2/10/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/10/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/10/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 2/10/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/10/2022 Corrections Issued RAUL OLAGI
Final 4/14/2022 Corrections Issued MICHAEL TEMPLE
Green Building Final 4/14/2022 Approved MICHAEL TEMPLE
Smoke Detectors 4/14/2022 Approved MICHAEL TEMPLE
Final 4/29/2022 OK to Issue CofO MICHAEL TEMPLE