13685 N GARRICK AVE 91342

Certificate Information: 13685 N GARRICK AVE 91342

Application / Permit
19014-20000-06137
Plan Check / Job No.
B19VN19629
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
24'3" X 31' X 10.5" IRR. SHAPE ADDITION AND (E) 18' X 20' GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 12/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/13/2019 PINANK PATEL
Corrections Issued 11/14/2019 PINANK PATEL
Building Plans Picked Up 11/20/2019 APPLICANT
Plan Check Approved 12/6/2019 PINANK PATEL
Issued 12/6/2019 LADBS
CofO in Progress 8/1/2020 MISAEL ESPARZA
CofO Issued 8/26/2020 MICHAEL SMITH
Permit Finaled 8/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/21/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/21/2019 ADRIAN CASTRO
Sewer availability Cleared 11/21/2019 ADRIAN CASTRO
Low Impact Development Cleared 12/4/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/6/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/2/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 2/7/2020 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/6/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/6/2020 Not Ready for Inspection JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 3/6/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 3/10/2020 Approved TROY SANDERS
Drywall Nailing 3/13/2020 Approved TROY SANDERS
Interior/Exterior Lathing 3/13/2020 Approved TROY SANDERS
Interior/Exterior Lathing 3/26/2020 Approved TROY SANDERS
Gas Test 5/15/2020 Approved TROY SANDERS
Service/Power Release 6/3/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 6/4/2020 Approved TROY SANDERS
ELECTRICAL-Final 6/4/2020 Approved TROY SANDERS
Final 6/4/2020 Not Ready for Inspection TROY SANDERS
Green Building Final 6/4/2020 Not Ready for Inspection TROY SANDERS
Green Building Rough 6/4/2020 Approved TROY SANDERS
HVAC-Final 6/4/2020 Approved TROY SANDERS
PLUMBING-Final 6/4/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 6/4/2020 Approved TROY SANDERS
Grading Pre-Inspection 6/5/2020 Not Ready for Inspection TROY SANDERS
Final 6/29/2020 OK to Issue CofO GREGG CUMMINGS
Green Building Final 6/29/2020 Approved GREGG CUMMINGS