12406 W SARAH ST 91604

Certificate Information: 12406 W SARAH ST 91604

Application / Permit
19014-20000-06130
Plan Check / Job No.
B19VN19612
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 18'-2" DETACHED GARAGE AND ADD 10'-4" X 15'-2" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/15/2019 JENNIFER LEE
Corrections Issued 11/15/2019 JENNIFER LEE
Plan Check Approved 1/21/2020 ANGELICA MARTINEZ
Issued 1/21/2020 LADBS
CofO in Progress 6/24/2020 ARAM AVEDISIAN
Permit Finaled 7/16/2020 MICHAEL SMITH
CofO Issued 7/16/2020 MICHAEL SMITH
Permit Finaled 7/16/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/11/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 12/11/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 12/11/2019 JAMES MORALEZ
Sewer availability Cleared 1/8/2020 MARKOS PEREZ-BRAN
Construction near power lines Cleared 1/17/2020 OSCAR CASTRO

Contact Information

Contractor Valley Builder & Remodeling; Lic. No.: 820243-B 5632 VAN NUYS BLVD #1300      SHERMAN OAKS, CA 91403
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2020 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 3/12/2020 Not Ready for Inspection BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/10/2020 Approved RAYMOND KEHOE
HVAC-Rough 4/10/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 4/10/2020 Not Ready for Inspection RAYMOND KEHOE
Wood Frame 4/10/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 4/15/2020 Approved TROY SANDERS
PLUMBING-Rough 4/15/2020 Partial Approval TROY SANDERS
Insulation 4/16/2020 Approved JOHN HAYES
PLUMBING-Rough 4/16/2020 Approved JOHN HAYES
Drywall Nailing 4/22/2020 Partial Approval JEFFREY PARD
Green Building Rough 4/22/2020 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 4/22/2020 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 4/22/2020 Approved GREGG CUMMINGS
Sewer 6/5/2020 Approved ARAM AVEDISIAN
Underground Mechanical 6/5/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/22/2020 Approved ARAM AVEDISIAN
Drywall Nailing 6/22/2020 Approved ARAM AVEDISIAN
Final 6/22/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 6/22/2020 Approved ARAM AVEDISIAN
Green Building Rough 6/22/2020 Approved ARAM AVEDISIAN
MERV13>=Final 6/22/2020 Approved ARAM AVEDISIAN
MERV13>=Rough 6/22/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 6/22/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/24/2020 Approved ARAM AVEDISIAN
Final 6/24/2020 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 6/24/2020 Approved ARAM AVEDISIAN
PLUMBING-Final 6/24/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Approved ARAM AVEDISIAN