6208 E BURWOOD AVE 90042
Certificate Information: 6208 E BURWOOD AVE 90042
- Application / Permit
- 19014-20000-06115
- Plan Check / Job No.
- B19VN19566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 10'-1" X 12'-10" TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB494 & SB229. ALL WORKS ARE PER DESIGN
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/25/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2019 | ALDOUS CHIC |
| Corrections Issued | 11/12/2019 | ALDOUS CHIC |
| Plan Check Approved | 11/22/2019 | ROSENDO MEDINA |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 3/24/2020 | ENRIQUE MIRELES |
| Permit Finaled | 5/25/2020 | DEROLD HAUFF |
| CofO Issued | 5/25/2020 | DEROLD HAUFF |
| Permit Finaled | 5/25/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/22/2019 | ALDOUS CHIC |
Contact Information
| Contractor | Liston Jim; Lic. No.: 514452-B | 231 E ALESSANDRO BL #A-157 RIVERSIDE, CA 92508 |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2020 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 2/13/2020 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 2/14/2020 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/20/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/20/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/20/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/21/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/21/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/26/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 2/26/2020 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 2/26/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 2/27/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/2/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/2/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/2/2020 | Approved | ENRIQUE MIRELES |
| Final | 3/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 3/17/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/17/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 3/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/23/2020 | Approved | ENRIQUE MIRELES |
| Final | 3/23/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/23/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/23/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/23/2020 | Approved | ENRIQUE MIRELES |
| Final | 3/24/2020 | OK to Issue CofO | ENRIQUE MIRELES |