13745 W HART ST 91405
Certificate Information: 13745 W HART ST 91405
- Application / Permit
- 19014-20000-06112
- Plan Check / Job No.
- B19VN19556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 25'-0" X 45'-0" IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 11/12/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/13/2019 | APPLICANT |
| Plan Check Approved | 1/24/2020 | JEROME MAGAT PALMA |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 2/17/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 2/17/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 4/22/2021 | MICHAEL SMITH |
| CofO Issued | 4/22/2021 | MICHAEL SMITH |
| Permit Finaled | 4/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 12/20/2019 | JORGE MEJIA LEMUS |
| Construction near power lines | Cleared | 1/7/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/23/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Markas Design & Construction; Lic. No.: 832632-B | 6022 VANTAGE AVENUE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/25/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/26/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/2/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/5/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/27/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 4/14/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/14/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/14/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 4/14/2020 | Approved | GREGG CUMMINGS |
| Wood Frame | 4/14/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/24/2020 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 4/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/24/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/24/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/11/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/11/2020 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/11/2020 | Conditional Approval | MISAEL ESPARZA |
| Sewer | 5/11/2020 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 5/21/2020 | Approved | MISAEL ESPARZA |
| Insulation | 5/21/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/21/2020 | Partial Approval | MISAEL ESPARZA |
| Sewer | 5/21/2020 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/21/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/27/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/8/2020 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 6/8/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/2/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 11/2/2020 | Approved | WILLIAM KUEHN |
| Final | 11/2/2020 | Corrections Issued | WILLIAM KUEHN |
| Gas Test | 11/2/2020 | Approved | WILLIAM KUEHN |
| Green Building Final | 11/2/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 11/2/2020 | Approved | WILLIAM KUEHN |
| HVAC-Final | 11/2/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/2/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 11/2/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 11/2/2020 | Not Required | WILLIAM KUEHN |
| Smoke Detectors | 11/2/2020 | Approved | WILLIAM KUEHN |
| Final | 12/10/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 2/10/2021 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 2/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/16/2021 | OK to Issue CofO | ARTHUR SARGSYAN |