22549 W BERDON ST 91367
Certificate Information: 22549 W BERDON ST 91367
- Application / Permit
- 19014-20000-06111
- Plan Check / Job No.
- B19VN19548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 34'9" x 18'5" (IRR. SHAPE) TO REAR FOR BEDROOM, LAUNDRY, AND EXPAND KITCHEN.
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | JEFFREY TANGONAN |
| Corrections Issued | 11/13/2019 | JEFFREY TANGONAN |
| Plan Check Approved | 1/27/2020 | ARTIN ZARUKIAN |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 10/21/2020 | TROY SANDERS |
| Permit Finaled | 10/21/2020 | JOHN JANSON |
| CofO Issued | 10/21/2020 | JOHN JANSON |
| Permit Finaled | 10/21/2020 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/24/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 1/27/2020 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 1/27/2020 | JEFFREY TANGONAN |
| Roof/Waste drainage to street | Cleared | 1/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/27/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Express Elec & Const Co; Lic. No.: 625249-B | 537 HAMPTON RD BURBANK, CA 91504 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/23/2020 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/25/2020 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 4/10/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/14/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/12/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/12/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 5/12/2020 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 5/12/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/19/2020 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 5/29/2020 | Approved | HENRY KIM |
| Insulation | 5/29/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 10/14/2020 | Approved | TROY SANDERS |
| Final | 10/14/2020 | Corrections Issued | TROY SANDERS |
| Green Building Final | 10/14/2020 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 10/14/2020 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 10/14/2020 | Approved | TROY SANDERS |
| Final | 10/19/2020 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/19/2020 | Approved | TROY SANDERS |