22549 W BERDON ST 91367

Certificate Information: 22549 W BERDON ST 91367

Application / Permit
19014-20000-06111
Plan Check / Job No.
B19VN19548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 34'9" x 18'5" (IRR. SHAPE) TO REAR FOR BEDROOM, LAUNDRY, AND EXPAND KITCHEN.
Permit Issued
Issued on 2/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 JEFFREY TANGONAN
Corrections Issued 11/13/2019 JEFFREY TANGONAN
Plan Check Approved 1/27/2020 ARTIN ZARUKIAN
Issued 2/28/2020 LADBS
CofO in Progress 10/21/2020 TROY SANDERS
Permit Finaled 10/21/2020 JOHN JANSON
CofO Issued 10/21/2020 JOHN JANSON
Permit Finaled 10/21/2020 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 1/24/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 1/27/2020 ADRIAN CASTRO
GPI Written Notices Cleared 1/27/2020 JEFFREY TANGONAN
Grading Pre-Inspection Cleared 1/27/2020 JEFFREY TANGONAN
Roof/Waste drainage to street Cleared 1/27/2020 ADRIAN CASTRO
Sewer availability Cleared 1/27/2020 ADRIAN CASTRO

Contact Information

Contractor Express Elec & Const Co; Lic. No.: 625249-B 537 HAMPTON RD      BURBANK, CA 91504

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/23/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 3/25/2020 Approved JOHN KIDWELL
PLUMBING-Rough 4/10/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 4/14/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 5/12/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 5/12/2020 Approved JOHN KIDWELL
Green Building Rough 5/12/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 5/12/2020 Approved JOHN KIDWELL
PLUMBING-Rough 5/12/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/19/2020 Partial Approval JOHN KIDWELL
Drywall Nailing 5/29/2020 Approved HENRY KIM
Insulation 5/29/2020 Approved HENRY KIM
BUILDING-Rough-Frame 10/14/2020 Approved TROY SANDERS
Final 10/14/2020 Corrections Issued TROY SANDERS
Green Building Final 10/14/2020 Corrections Issued TROY SANDERS
Green Building Rough 10/14/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 10/14/2020 Approved TROY SANDERS
Final 10/19/2020 OK to Issue CofO TROY SANDERS
Green Building Final 10/19/2020 Approved TROY SANDERS