5011 E MERIDIAN ST 90042

Certificate Information: 5011 E MERIDIAN ST 90042

Application / Permit
19014-20000-06101
Plan Check / Job No.
B19VN19507
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DET. GARAGE AND 2-STORY ADDITION FOR AN ACCESSORY DWELLING UNIT PER AB 229 AND SB 1069
Permit Issued
Issued on 1/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 JEFFREY TANGONAN
Corrections Issued 11/13/2019 JEFFREY TANGONAN
Building Plans Picked Up 11/13/2019 APPLICANT
Plan Check Approved 12/30/2019 JEFFREY TANGONAN
Issued 1/9/2020 LADBS
CofO in Progress 12/1/2021 CRAIG VAUGHAN
Permit Finaled 12/18/2021 DEROLD HAUFF
CofO Issued 12/18/2021 DEROLD HAUFF
Permit Finaled 12/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/19/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/19/2019 LEE GUILBEAUX
Sewer availability Cleared 11/19/2019 LEE GUILBEAUX
Low Impact Development Cleared 12/16/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/19/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Sunshine Builders Inc; Lic. No.: 1008306-B 7120 HAVENHURST AVE STE 113      VAN NUYS, CA 91406
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/19/2020 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/19/2020 Partial Approval CRAIG VAUGHAN
Underground Mechanical 5/21/2020 Corrections Issued RUBEN SALAS
Underground Mechanical 5/27/2020 Approved COREY HUPP
BUILDING-Rough-Frame 6/8/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 6/8/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 6/8/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/8/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/8/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/15/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/15/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/15/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/15/2020 Approved CRAIG VAUGHAN
Shower Pan 6/15/2020 Approved CRAIG VAUGHAN
Wood Frame 6/15/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 7/22/2020 Partial Approval CRAIG VAUGHAN
Insulation 7/30/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 7/30/2020 Partial Approval RUBEN SALAS
Drywall Nailing 8/5/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/5/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/20/2020 Approved CRAIG VAUGHAN
Final 11/20/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 11/20/2020 Approved CRAIG VAUGHAN
Green Building Final 11/20/2020 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 11/20/2020 Approved CRAIG VAUGHAN
Final 4/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 4/15/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Not Ready CRAIG VAUGHAN
Final 7/15/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 11/29/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 11/29/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Not Ready CRAIG VAUGHAN
ELECTRICAL-Final 11/30/2021 Approved CRAIG VAUGHAN
Final 11/30/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 11/30/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 11/30/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved CRAIG VAUGHAN