5011 E MERIDIAN ST 90042
Certificate Information: 5011 E MERIDIAN ST 90042
- Application / Permit
- 19014-20000-06101
- Plan Check / Job No.
- B19VN19507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DET. GARAGE AND 2-STORY ADDITION FOR AN ACCESSORY DWELLING UNIT PER AB 229 AND SB 1069
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | JEFFREY TANGONAN |
| Corrections Issued | 11/13/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 11/13/2019 | APPLICANT |
| Plan Check Approved | 12/30/2019 | JEFFREY TANGONAN |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 12/1/2021 | CRAIG VAUGHAN |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
| CofO Issued | 12/18/2021 | DEROLD HAUFF |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 12/16/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Sunshine Builders Inc; Lic. No.: 1008306-B | 7120 HAVENHURST AVE STE 113 VAN NUYS, CA 91406 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/19/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/19/2020 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 5/21/2020 | Corrections Issued | RUBEN SALAS |
| Underground Mechanical | 5/27/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/8/2020 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/8/2020 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 6/8/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 6/8/2020 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/8/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/15/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 6/15/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/15/2020 | Approved | CRAIG VAUGHAN |
| Shower Pan | 6/15/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 6/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/22/2020 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 7/30/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 8/5/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/5/2020 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/20/2020 | Approved | CRAIG VAUGHAN |
| Final | 11/20/2020 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/20/2020 | Approved | CRAIG VAUGHAN |
| Green Building Final | 11/20/2020 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 11/20/2020 | Approved | CRAIG VAUGHAN |
| Final | 4/15/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 4/15/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 7/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/15/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 11/29/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/29/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/30/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/30/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 11/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/30/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | CRAIG VAUGHAN |