5537 W 3RD ST 90036

Certificate Information: 5537 W 3RD ST 90036

Application / Permit
19014-20000-06099
Plan Check / Job No.
B19VN19502
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
MAJOR REMODEL TO (E) 4-CAR GARAGE; ONLY 11'7-1/2" LONG WALL TO REMAIN TO MAKE A 31'11-1/2 X 21'11-1/2" IRREGULAR SHAPED 1ST FLOOR 2-CAR GARAGE AND A 28'5-1/2"X21'11-1/2" IRREGULAR SHAPED ADU ON THE 2ND FLOOR PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 MARVEL DELACRUZ
Corrections Issued 11/17/2019 MARVEL DELACRUZ
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Building Plans Picked Up 11/20/2019 APPLICANT
Applicant returned to address corrections 9/16/2020 MARVEL DELACRUZ
Green Plans Picked Up 8/4/2021 APPLICANT
Plan Check Approved 8/16/2021 MARVEL DELACRUZ
Issued 9/9/2021 APPLICANT
CofO in Progress 8/23/2023 ALIZAH MAYAGOITIA
Permit Finaled 8/29/2023 DEROLD HAUFF
CofO Issued 8/29/2023 DEROLD HAUFF
Permit Finaled 8/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/11/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/11/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 12/30/2019 AARON COSTA
Construction near power lines Cleared 2/27/2020 ERNEST FRESQUEZ
Construction within easement Cleared 2/27/2020 ERNEST FRESQUEZ
Tenant Habitability Plan Cleared 7/20/2020 PHILLIP MUNGUIA
Low Impact Development Cleared 7/29/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/7/2020 ELAINE LEI
Address approval Cleared 10/26/2020 THOMAS LANG
Construction near power lines Cleared 6/14/2021 RIDWAN HARDY
Construction within easement Cleared 6/14/2021 RIDWAN HARDY

Contact Information

Contractor Ben Porat Moshe M; Lic. No.: 963181-B P O BOX 48603      LOS ANGELES, CA 90048
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2021 Approved ARTHUR SARGSYAN
METHANE-Barrier 12/10/2021 Approved ARTHUR SARGSYAN
METHANE-Subgrade 12/10/2021 Approved ARTHUR SARGSYAN
Sewer 12/10/2021 Approved ARTHUR SARGSYAN
Masonry Wall/Backfill 12/22/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/10/2022 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 1/10/2022 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval ARTHUR SARGSYAN
Green Building Rough 1/10/2022 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 1/10/2022 Not Ready for Inspection ARTHUR SARGSYAN
Masonry Wall/Backfill 1/10/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/11/2022 Corrections Issued CRAIG DAVIS
Green Building Rough 2/11/2022 Not Ready for Inspection CRAIG DAVIS
METHANE-Rough 2/11/2022 Corrections Issued CRAIG DAVIS
Rough-Elec/Plmb/HVAC 2/11/2022 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 2/24/2022 Approved ARTHUR SARGSYAN
HVAC-Rough 2/24/2022 Approved ARTHUR SARGSYAN
Insulation 2/24/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 2/24/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 2/24/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 3/11/2022 Approved ARTHUR SARGSYAN
Green Building Rough 3/11/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/22/2022 Approved ARTHUR SARGSYAN
Shower Pan 3/22/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/30/2022 Approved ADAM ESCOTO
ELECTRICAL-Final 6/30/2022 Corrections Issued ADAM ESCOTO
Final 6/30/2022 Corrections Issued ADAM ESCOTO
Green Building Final 6/30/2022 Approved ADAM ESCOTO
HVAC-Final 6/30/2022 Corrections Issued ADAM ESCOTO
METHANE-Final 6/30/2022 Approved ADAM ESCOTO
METHANE-Rough 6/30/2022 Approved ADAM ESCOTO
PLUMBING-Final 6/30/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved ADAM ESCOTO
Smoke Detectors 6/30/2022 Approved ADAM ESCOTO
ELECTRICAL-Final 7/14/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 7/14/2022 Approved ALIZAH MAYAGOITIA
Final 8/22/2023 OK to Issue CofO ALIZAH MAYAGOITIA