7036 N YOLANDA AVE 91335
Certificate Information: 7036 N YOLANDA AVE 91335
- Application / Permit
- 19014-20000-06097
- Plan Check / Job No.
- B19VN19499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- KITCHEN & BATHROOM REMODEL TO (E) SFD, 3'-3" X 7'-9" ADDITION TO CONVERT (E) DEN TO A (N) BEDROOM. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 11/18/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 11/8/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 11/18/2019 | HAYATO TSUCHIYA |
| Issued | 11/18/2019 | LADBS |
| CofO in Progress | 3/17/2021 | VINCENT HANLEY |
| Permit Finaled | 3/17/2021 | JOHN JANSON |
| CofO Issued | 3/17/2021 | JOHN JANSON |
| Permit Finaled | 3/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/18/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2020 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/18/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/1/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/11/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/11/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 5/11/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/3/2020 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/3/2020 | Partial Approval | VINCENT HANLEY |
| Insulation | 6/16/2020 | Corrections Issued | DONALD SUNSERI |
| HVAC-Rough | 6/18/2020 | Corrections Issued | VINCENT HANLEY |
| Insulation | 6/18/2020 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/25/2020 | Approved | VINCENT HANLEY |
| Insulation | 6/25/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/30/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/19/2020 | Approved | DAVID SANDOVAL |
| Final | 10/19/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/19/2020 | Approved | DAVID SANDOVAL |
| Green Building Final | 10/19/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 10/19/2020 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 10/19/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Final | 3/10/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 3/10/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 3/10/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/10/2021 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 3/10/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/15/2021 | Approved | VINCENT HANLEY |
| Final | 3/15/2021 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/15/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/15/2021 | Approved | VINCENT HANLEY |