20441 W MAYALL ST 91311
Certificate Information: 20441 W MAYALL ST 91311
- Application / Permit
- 19014-20000-06074
- Plan Check / Job No.
- B19VN19433
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 10'-0" X 24'-0" REAR PATIO COVER AND ADD 20'-0" X 23'-4" TO EXTEND (2) EXISTING BEDROOMS PER WFPP
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | TROY DEGUZMAN |
| Corrections Issued | 11/7/2019 | TROY DEGUZMAN |
| Applicant returned to address corrections | 12/16/2019 | JENNIFER LEE |
| Plan Check Approved | 1/29/2020 | HAYATO TSUCHIYA |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 8/21/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
| CofO Issued | 9/20/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 1/29/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 1/29/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 6/2/2020 | Corrections Issued | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 7/13/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 9/30/2020 | Approved | JEFFREY PARD |
| Insulation | 10/7/2020 | Approved | JEFFREY PARD |
| Drywall Nailing | 10/15/2020 | Approved | DONALD SUNSERI |
| Excavation/Setback/Form/Re-Bar | 7/9/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 7/9/2021 | Corrections Issued | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 7/20/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/18/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/18/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/20/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Deputy Wood Construction | 8/23/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 8/31/2021 | Approved | DEANDRE HOFFMAN |
| Insulation | 9/2/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 9/9/2021 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | DAVID SCANTLIN |
| Final | 2/3/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/3/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/3/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/3/2023 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 3/8/2023 | Approved | DAVID SCANTLIN |
| Final | 8/21/2025 | OK to Issue CofO | MICHAEL PELHAM |