(N) 12'-6" x 12'-6" ADDITION TO (E) SINGLE FAMILY DWELLING TO ADD A NEW MASTER BEDROOM AND ALTER (E) BEDROOM AND BATHROOM TO ADD (N) CLOSET AND BATHROOM FOR MASTER BEDROOM.
Permit Issued
Issued on 3/12/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 SEAN SHAHMIRI
Corrections Issued 12/2/2019 SEAN SHAHMIRI
Quality Review Completed 12/12/2019 OMID HEDAYAT
Green Plans Picked Up 12/12/2019 APPLICANT
Building Plans Picked Up 12/26/2019 APPLICANT
Plan Check Approved 3/6/2020 SEAN SHAHMIRI
Issued 3/12/2020 LADBS
CofO in Progress 6/29/2021 MICHAEL TEMPLE
Permit Finaled 7/17/2021 MICHAEL SMITH
CofO Issued 7/17/2021 MICHAEL SMITH
Permit Finaled 7/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/9/2020 GABRIEL ROBLES
Low Impact Development Cleared 2/25/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/25/2020 JOHN LIN
Green Code Cleared 3/6/2020 MICHAEL AYERS

Contact Information

Contractor Foundation To Roof Inc; Lic. No.: 767761-B 10800 SOUTH LA CIENEGA BL      INGLEWOOD, CA 90304
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 7/14/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Approved MARK JOHNSON
PLUMBING-Rough 7/14/2020 Not Ready for Inspection MARK JOHNSON
Wood Frame 7/14/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 8/20/2020 Conditional Approval MICHAEL TEMPLE
Interior/Exterior Lathing 8/20/2020 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 8/20/2020 Approved MICHAEL TEMPLE
HVAC-Rough 9/1/2020 Approved MARK JOHNSON
Insulation 9/1/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 9/17/2020 Approved MARK JOHNSON
Drywall Nailing 9/17/2020 Partial Approval MARK JOHNSON
Green Building Rough 9/17/2020 Approved MARK JOHNSON
MERV13>=Rough 9/17/2020 Approved MARK JOHNSON
Shower Pan 9/17/2020 Not Ready for Inspection MARK JOHNSON
Shower Pan 10/21/2020 Approved MARK JOHNSON
Drywall Nailing 2/11/2021 Approved MARK JOHNSON
Final 2/11/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 2/11/2021 Approved MARK JOHNSON
Green Building Final 2/11/2021 Approved MARK JOHNSON
MERV13>=Final 2/11/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Not Ready MARK JOHNSON
Service/Power Release 2/11/2021 Not Required MARK JOHNSON
Smoke Detectors 2/11/2021 Approved MARK JOHNSON
Final 2/19/2021 Corrections Issued MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Approved MARK JOHNSON
ELECTRICAL-Final 6/21/2021 Approved MARK JOHNSON
Final 6/21/2021 OK to Issue CofO MARK JOHNSON