7438 N LURLINE AVE 91306
Certificate Information: 7438 N LURLINE AVE 91306
- Application / Permit
- 19014-20000-06060
- Plan Check / Job No.
- B19VN19369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-2" X 20'-2" DETACHED GARAGE AND ADD 17'-4.5" X 21'-7.5" TO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- CofO Issued on 4/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | RAPHAEL ROSAS |
| Corrections Issued | 11/7/2019 | RAPHAEL ROSAS |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Plan Check Approved | 7/6/2020 | RAPHAEL ROSAS |
| Issued | 7/30/2020 | APPLICANT |
| CofO in Progress | 4/21/2021 | HENRY KIM |
| Permit Finaled | 4/28/2021 | JOHN JANSON |
| CofO Issued | 4/28/2021 | JOHN JANSON |
| Permit Finaled | 4/28/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2019 | GUILLERMO PETRA |
| Permit | Cleared | 11/12/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 11/12/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/4/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 2/10/2020 | RIDWAN HARDY |
| Trees in Parkway | Cleared | 6/3/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 8/14/2020 | Corrections Issued | HENRY KIM |
| Sewer | 8/14/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 8/19/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 8/19/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 8/19/2020 | Approved | HENRY KIM |
| Sewer | 8/19/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 8/21/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Partial Approval | HENRY KIM |
| Insulation | 9/14/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 9/30/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 10/16/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/30/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 10/30/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | HENRY KIM |
| Green Building Rough | 11/4/2020 | Approved | HENRY KIM |
| HVAC-Rough | 11/4/2020 | Partial Approval | HENRY KIM |
| Insulation | 11/4/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 11/4/2020 | Approved | HENRY KIM |
| Drywall Nailing | 11/18/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 11/18/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 11/18/2020 | Approved | HENRY KIM |
| Shower Pan | 11/18/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/21/2020 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Approved | TROY SANDERS |
| PLUMBING-Final | 12/21/2020 | Approved | TROY SANDERS |
| Smoke Detectors | 12/21/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 2/24/2021 | Corrections Issued | HENRY KIM |
| Final | 2/24/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 2/24/2021 | Approved | HENRY KIM |
| HVAC-Final | 2/24/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 2/24/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | HENRY KIM |
| ELECTRICAL-Final | 3/15/2021 | Corrections Issued | HENRY KIM |
| Final | 3/15/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 3/15/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 3/15/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 4/14/2021 | Corrections Issued | HENRY KIM |
| Final | 4/14/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 4/14/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 4/14/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 4/21/2021 | Approved | HENRY KIM |
| Final | 4/21/2021 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 4/21/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 4/21/2021 | Approved | HENRY KIM |