1560 W FAIR PARK AVE 90041

Certificate Information: 1560 W FAIR PARK AVE 90041

Application / Permit
19014-20000-06059
Plan Check / Job No.
B19VN19368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
35'-6" X 32'-8" IRREGULAR SHAPE ADDITION AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING FOR (3) NEW BEDROOMS, CLOSET, AND FULL BATHROOM. NEW 17' X 22' OCCUPIED ROOF DECK WITH EXTERIOR STAIR ACCESS. BUILDING SHALL BE EQUIPPED WITH AUTOMATIC FIRE SPRINKLER SYSTEM.
Permit Issued
Issued on 7/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ROSENDO MEDINA
Green Plans Picked Up 11/19/2019 APPLICANT
Corrections Issued 12/11/2019 ROSENDO MEDINA
Quality Review Completed 12/12/2019 GUANG MIN TUNG
Building Plans Picked Up 12/16/2019 APPLICANT
Plan Check Approved 3/9/2020 ROSENDO MEDINA
Issued 7/8/2020 APPLICANT
CofO in Progress 3/3/2021 CRAIG VAUGHAN
Permit Finaled 3/24/2021 DEROLD HAUFF
CofO Issued 3/24/2021 DEROLD HAUFF
Permit Finaled 3/24/2021 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 12/6/2019 LOURDES RAMIRO
Eng Process Fee Ord 176,300 Cleared 1/30/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 1/30/2020 TIMOTHY POWELL
Sewer availability Cleared 1/30/2020 GUILLERMO PETRA
Green Code Cleared 2/5/2020 DAVID MATSON
Low Impact Development Cleared 2/10/2020 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 2/11/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 2/11/2020 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 2/25/2020 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/13/2020 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/14/2020 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 7/15/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 7/15/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/31/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/31/2020 Partial Approval CRAIG VAUGHAN
Underground Mechanical 7/31/2020 Partial Approval CRAIG VAUGHAN
Wood Frame 7/31/2020 Partial Approval CRAIG VAUGHAN
Insulation 8/3/2020 Partial Approval DAVID MATSON
Wood Frame 8/5/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/17/2020 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 9/15/2020 Corrections Issued CRAIG VAUGHAN
Reinforced Masonry Frame 9/15/2020 Corrections Issued CRAIG VAUGHAN
Deputy Drilled-In Anchors 9/16/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 9/18/2020 Corrections Issued HAMIK HARTOUNIAN
Reinforced Masonry Frame 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/22/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 10/1/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 10/7/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/15/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 10/15/2020 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 10/15/2020 Approved CRAIG VAUGHAN
HVAC-Rough 10/15/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/15/2020 Approved CRAIG VAUGHAN
Structural Steel Frame 10/15/2020 Corrections Issued CRAIG VAUGHAN
Wood Frame 10/15/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 10/21/2020 Approved CRAIG VAUGHAN
Structural Steel Frame 10/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 10/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Insulation 10/23/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/23/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/27/2020 Approved CRAIG VAUGHAN
HVAC-Rough 10/27/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/27/2020 Partial Approval CRAIG VAUGHAN
Structural Steel Frame 10/27/2020 Partial Approval CRAIG VAUGHAN
Wood Frame 10/27/2020 Approved CRAIG VAUGHAN
Insulation 10/29/2020 Approved CRAIG VAUGHAN
Structural Steel Frame 10/29/2020 Conditional Approval CRAIG VAUGHAN
Drywall Nailing 11/6/2020 Approved CRAIG VAUGHAN
Green Building Rough 11/6/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/13/2020 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 11/18/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/18/2020 Off-Hour Fees Due
BUILDING-Rough-Frame 12/17/2020 Approved OSVALDO PARAMO
Final 12/17/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/17/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/24/2020 Approved CRAIG VAUGHAN
Piling/Pier/Caisson 12/29/2020 No Access for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/22/2021 SGSOV Not Ready CRAIG VAUGHAN
Final 1/27/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/27/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 1/27/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 2/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 2/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 2/24/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 2/26/2021 Corrections Issued CRAIG VAUGHAN
Final 2/26/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 2/26/2021 Approved CRAIG VAUGHAN
HVAC-Final 2/26/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/26/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/26/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/2/2021 Approved CRAIG VAUGHAN
Final 3/2/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 3/2/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 3/2/2021 Approved CRAIG VAUGHAN