3141 N GLENMANOR PL 90039
Certificate Information: 3141 N GLENMANOR PL 90039
- Application / Permit
- 19014-20000-06043
- Plan Check / Job No.
- B19VN19322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 12' X 9'-2" ADDITION TO DETACHED 1-STORY GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SERGIO MUNIZ |
| Corrections Issued | 11/27/2019 | SERGIO MUNIZ |
| Green Plans Picked Up | 12/9/2019 | APPLICANT |
| Quality Review Completed | 12/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 12/17/2019 | APPLICANT |
| Plan Check Approved | 1/23/2020 | SERGIO MUNIZ |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 2/28/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 12/30/2019 | DAVID MATSON |
| Address approval | Cleared | 1/17/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/17/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/17/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/21/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Sewer | 1/21/2021 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/21/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/17/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/21/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/21/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 6/21/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/21/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/21/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/27/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/2/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/8/2021 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 9/13/2021 | Approved | CHARLES BOGHOSKHAN |
| Final | 2/3/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/3/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/3/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 2/25/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 2/25/2022 | Approved | HAMIK HARTOUNIAN |