4560 N STANSBURY AVE 91423

Certificate Information: 4560 N STANSBURY AVE 91423

Application / Permit
19014-20000-06027
Plan Check / Job No.
B19VN19253
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Green Plans Picked Up 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 SELLA BENYAMIN
Corrections Issued 11/18/2019 SELLA BENYAMIN
Quality Review Completed 11/19/2019 STEVEN KIM
Building Plans Picked Up 11/20/2019 APPLICANT
Plan Check Approved 12/20/2019 SELLA BENYAMIN
Issued 1/6/2020 LADBS
CofO in Progress 3/18/2021 BRENDAN LOONEY
CofO Issued 5/15/2021 MICHAEL SMITH
Permit Finaled 5/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2019 ADRIAN CASTRO
Green Code Cleared 12/17/2019 MICHAEL AYERS
Low Impact Development Cleared 12/17/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/17/2019 GUILLERMO PETRA
Sewer availability Cleared 12/17/2019 ADRIAN CASTRO

Contact Information

Contractor Rosegold Builders Inc; Lic. No.: 1041947-B 12200 RIVERSIDE DRIVE UNIT 4      VALLEY VILLAGE, CA 91607

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 2/19/2020 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 2/24/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 3/5/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 6/12/2020 Not Ready for Inspection CHARLES POWELL
Green Building Rough 6/12/2020 Not Ready for Inspection CHARLES POWELL
MERV13>=Rough 6/12/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 6/12/2020 Approved CHARLES POWELL
Deputy Wood Construction 6/15/2020 Partial Approval CHARLES POWELL
ELECTRICAL-Rough 6/19/2020 Approved CHARLES POWELL
HVAC-Rough 6/19/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 7/7/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 7/30/2020 Approved CHARLES POWELL
Green Building Rough 7/30/2020 Approved CHARLES POWELL
MERV13>=Rough 7/30/2020 Approved CHARLES POWELL
Insulation 8/3/2020 Approved CHARLES POWELL
Underground Mechanical 8/11/2020 Partial Approval CHARLES POWELL
Underground Mechanical 8/14/2020 Approved CHARLES POWELL
Drywall Nailing 8/25/2020 Approved PIERRE VEGA
ELECTRICAL-Final 2/1/2021 Approved CHARLES POWELL
HVAC-Final 2/1/2021 Not Ready for Inspection CHARLES POWELL
MERV13>=Final 2/1/2021 Corrections Issued CHARLES POWELL
PLUMBING-Final 2/1/2021 Approved CHARLES POWELL
Final 2/3/2021 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 2/3/2021 Approved CHARLES POWELL
Green Building Final 2/3/2021 Approved CHARLES POWELL
HVAC-Final 2/3/2021 Not Ready for Inspection CHARLES POWELL
MERV13>=Final 2/3/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 2/3/2021 SGSOV Approved CHARLES POWELL
Smoke Detectors 2/3/2021 Approved CHARLES POWELL
HVAC-Final 2/16/2021 Approved BRENDAN LOONEY
Final 3/1/2021 Corrections Issued BRENDAN LOONEY
MERV13>=Final 3/1/2021 Approved BRENDAN LOONEY
Final 3/17/2021 OK to Issue CofO BRENDAN LOONEY