3812 S CARMONA AVE 90008
Certificate Information: 3812 S CARMONA AVE 90008
- Application / Permit
- 19014-20000-06007
- Plan Check / Job No.
- B19VN19197
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL , REMOVE WALLS BETWEEN KITCHEN & LIVING ROOM & DINING ROOM, ENCLOSE 4'-3" X 3'-3" PORTION OF PATIO FOR (N) BATHROOM, 11'-0" X 8'-0" CLOSET ADDITION TO (E) SFD TO ATTACH TO (E) GARAGE , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/8/2019
- Issuing Office
- Valley
- Current Status
- Issued on 11/8/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 11/5/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 11/8/2019 | RARES BODEA |
| Issued | 11/8/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2019 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 11/8/2019 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 11/8/2019 | ADRIAN CASTRO |
Contact Information
| Architect | Belak-Berger,, Charles Peter; Lic. No.: C13657 | 521 W. ROSECRANS AVE. GARDENA, CA 902481514 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/18/2019 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 12/18/2019 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 12/18/2019 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 12/18/2019 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 12/24/2019 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 12/24/2019 | Approved | HORACE FULTZ |
| Green Building Rough | 12/24/2019 | Approved | HORACE FULTZ |
| METHANE-Rough | 12/24/2019 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 12/24/2019 | Approved | HORACE FULTZ |
| Insulation | 1/2/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 1/8/2020 | Corrections Issued | COREY HUPP |
| Drywall Nailing | 1/14/2020 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2020 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 1/31/2020 | Not Ready for Inspection | COREY HUPP |
| Shower Pan | 1/31/2020 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| Gas Test | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| Insulation | 2/3/2020 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| Shower Pan | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| Wood Frame | 2/3/2020 | No Access for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/10/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 2/13/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 3/23/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 3/23/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 4/1/2020 | Approved | COREY HUPP |
| Sewer | 5/26/2020 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 6/16/2020 | Not Ready for Inspection | COREY HUPP |
| Final | 6/16/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 6/16/2020 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 6/16/2020 | Not Ready for Inspection | COREY HUPP |
| Drywall Nailing | 7/17/2020 | Approved | COREY HUPP |
| Final | 7/17/2020 | Corrections Issued | COREY HUPP |
| Green Building Final | 7/17/2020 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 7/17/2020 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 7/17/2020 | Approved | COREY HUPP |
| Final | 8/28/2020 | Partial Inspection | COREY HUPP |
| Final | 9/3/2020 | Corrections Issued | COREY HUPP |
| Final | 9/10/2020 | Conditional Approval | COREY HUPP |