16357-16359 W ARMSTEAD ST 91344
Certificate Information: 16357-16359 W ARMSTEAD ST 91344
- Application / Permit
- 19014-20000-05989
- Plan Check / Job No.
- B19VN19123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 22'-0" X 23'-8" ATTACHED GARAGE AND ADD 8'-0" X 23'-8" AND 5'-6" X 9'-0" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2019 | ALDOUS CHIC |
| Corrections Issued | 11/19/2019 | ALDOUS CHIC |
| Plan Check Approved | 3/9/2020 | JENNIFER LEE |
| Issued | 4/27/2020 | LADBS |
| CofO in Progress | 10/16/2020 | MARK JOHNSON |
| CofO Issued | 1/9/2021 | MICHAEL SMITH |
| Permit Finaled | 1/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 11/4/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/4/2019 | APEKSHYA BAJRACHARYA |
| Grading Pre-Inspection | Cleared | 3/2/2020 | ALDOUS CHIC |
| ZA Case | Cleared | 3/3/2020 | MIGUEL GAMBOA |
Contact Information
| Engineer | Abrahamian,, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2020 | Corrections Issued | MARK JOHNSON |
| Underground Mechanical | 6/4/2020 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 6/9/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 6/9/2020 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/24/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/24/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/26/2020 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | JOHN HAYES |
| Green Building Rough | 6/26/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/9/2020 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 7/9/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 7/9/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 7/9/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/9/2020 | Approved | MARK JOHNSON |
| Insulation | 7/16/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 7/16/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 7/23/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/15/2020 | Approved | MARK JOHNSON |
| Final | 9/15/2020 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Final | 9/15/2020 | Not Ready for Inspection | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Not Ready | MARK JOHNSON |
| Smoke Detectors | 9/15/2020 | Approved | MARK JOHNSON |
| Final | 9/23/2020 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 9/23/2020 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | MARK JOHNSON |
| Final | 10/6/2020 | Not Ready for Inspection | MARK JOHNSON |
| Final | 10/15/2020 | OK to Issue CofO | MARK JOHNSON |
| Special/Order Compliance | 12/22/2020 | Approved | MARK JOHNSON |