11333-11335 W UTOPIA AVE 90230

Certificate Information: 11333-11335 W UTOPIA AVE 90230

Application / Permit
19014-20000-05985
Plan Check / Job No.
B19VN19096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove all on grade structures except attached garage, front porch and portion of North & East side walls, rebuild with addition of irregular shape 33'5" x 49'10" and convert garage to accessory dwelling unit per AB494 & SB229. All works are per design
Permit Issued
Issued on 1/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2019 APPLICANT
Green Plans Picked Up 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ALDOUS CHIC
Corrections Issued 11/18/2019 ALDOUS CHIC
Quality Review Completed 11/19/2019 ABDUL CHEGENI
Building Plans Picked Up 11/21/2019 APPLICANT
Plan Check Approved 1/13/2020 ALDOUS CHIC
Issued 1/13/2020 LADBS
CofO in Progress 3/3/2021 ENRIQUE MIRELES
CofO Issued 5/17/2021 VINCENT COTTON
Permit Finaled 5/17/2021 VINCENT COTTON

Permit Application Clearance Information

Green Code Cleared 12/4/2019 AARON COSTA
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCIAL
Address approval Cleared 1/9/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/9/2020 JOHN LIN
Roof/Waste drainage to street Cleared 1/9/2020 JOHN LIN
Sewer availability Cleared 1/9/2020 JOHN LIN

Contact Information

Contractor Arrowhead Remodeling & Design Inc; Lic. No.: 935108-B 18345 VENTURA BLVD #212      TARZANA, CA 91356
Engineer Nirattisai,, Preston; Lic. No.: C85115 311 N 7TH ST APT G      BURBANK, CA 91501

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2020 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 3/16/2020 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 3/18/2020 Corrections Issued DAVID FEILER
Deputy Drilled-In Anchors 3/26/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/27/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 4/2/2020 Approved DAVID FEILER
Deputy Wood Construction 4/17/2020 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 4/20/2020 Partial Inspection DAVID FEILER
Green Building Rough 4/20/2020 Not Ready for Inspection DAVID FEILER
MERV13>=Rough 4/20/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/20/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 4/22/2020 Partial Approval DAVID FEILER
Wood Frame 4/24/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval DAVID FEILER
Deputy Wood Construction 5/21/2020 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 5/26/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 5/26/2020 Partial Approval DAVID FEILER
Wood Frame 5/26/2020 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 5/28/2020 Partial Approval DAVID FEILER
HVAC-Rough 5/28/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/28/2020 Approved DAVID FEILER
Wood Frame 5/28/2020 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 5/29/2020 No Access for Inspection DAVID FEILER
Wood Frame 6/8/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Approved JUAN VALENZUELA
Green Building Rough 6/9/2020 Not Ready for Inspection JUAN VALENZUELA
MERV13>=Rough 6/9/2020 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 6/15/2020 Approved OGANES TARAKHCHYAN
Shower Pan 6/15/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/17/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 6/19/2020 Approved JOHNNY MIRANDA
Green Building Rough 6/19/2020 Approved JOHNNY MIRANDA
Insulation 6/19/2020 Approved JOHNNY MIRANDA
MERV13>=Rough 6/19/2020 Approved JOHNNY MIRANDA
Drywall Nailing 6/26/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/16/2020 SGSOV Not Ready JOHNNY MIRANDA
Pre-Inspection 9/21/2020 Corrections Issued ENRIQUE MIRELES
Final 9/29/2020 Corrections Issued PIERRE VEGA
Green Building Final 9/29/2020 Not Ready for Inspection PIERRE VEGA
MERV13>=Final 9/29/2020 Not Ready for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 9/29/2020 Not Ready for Inspection PIERRE VEGA
Final 12/28/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/28/2020 Approved ENRIQUE MIRELES
MERV13>=Final 12/28/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/28/2020 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/28/2020 Approved ENRIQUE MIRELES
Service/Power Release 1/4/2021 Partial Approval ENRIQUE MIRELES
Final 3/3/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 3/3/2021 Approved ENRIQUE MIRELES
Special/Order Compliance 3/15/2021 Corrections Issued ENRIQUE MIRELES