11333-11335 W UTOPIA AVE 90230
Certificate Information: 11333-11335 W UTOPIA AVE 90230
- Application / Permit
- 19014-20000-05985
- Plan Check / Job No.
- B19VN19096
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Remove all on grade structures except attached garage, front porch and portion of North & East side walls, rebuild with addition of irregular shape 33'5" x 49'10" and convert garage to accessory dwelling unit per AB494 & SB229. All works are per design
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2019 | APPLICANT |
| Green Plans Picked Up | 11/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ALDOUS CHIC |
| Corrections Issued | 11/18/2019 | ALDOUS CHIC |
| Quality Review Completed | 11/19/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Plan Check Approved | 1/13/2020 | ALDOUS CHIC |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 3/3/2021 | ENRIQUE MIRELES |
| CofO Issued | 5/17/2021 | VINCENT COTTON |
| Permit Finaled | 5/17/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Green Code | Cleared | 12/4/2019 | AARON COSTA |
| Low Impact Development | Cleared | 1/7/2020 | ORVAL HERNANDEZ-MARCIAL |
| Address approval | Cleared | 1/9/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | JOHN LIN |
| Sewer availability | Cleared | 1/9/2020 | JOHN LIN |
Contact Information
| Contractor | Arrowhead Remodeling & Design Inc; Lic. No.: 935108-B | 18345 VENTURA BLVD #212 TARZANA, CA 91356 |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 311 N 7TH ST APT G BURBANK, CA 91501 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/3/2020 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 3/16/2020 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 3/18/2020 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 3/26/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/27/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 4/2/2020 | Approved | DAVID FEILER |
| Deputy Wood Construction | 4/17/2020 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/20/2020 | Partial Inspection | DAVID FEILER |
| Green Building Rough | 4/20/2020 | Not Ready for Inspection | DAVID FEILER |
| MERV13>=Rough | 4/20/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 4/20/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 4/22/2020 | Partial Approval | DAVID FEILER |
| Wood Frame | 4/24/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 5/21/2020 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 5/26/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 5/26/2020 | Partial Approval | DAVID FEILER |
| Wood Frame | 5/26/2020 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/28/2020 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 5/28/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/28/2020 | Approved | DAVID FEILER |
| Wood Frame | 5/28/2020 | Not Ready for Inspection | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 5/29/2020 | No Access for Inspection | DAVID FEILER |
| Wood Frame | 6/8/2020 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/9/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 6/9/2020 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/17/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/19/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/19/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 6/19/2020 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 6/19/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/26/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Not Ready | JOHNNY MIRANDA |
| Pre-Inspection | 9/21/2020 | Corrections Issued | ENRIQUE MIRELES |
| Final | 9/29/2020 | Corrections Issued | PIERRE VEGA |
| Green Building Final | 9/29/2020 | Not Ready for Inspection | PIERRE VEGA |
| MERV13>=Final | 9/29/2020 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 9/29/2020 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 9/29/2020 | Not Ready for Inspection | PIERRE VEGA |
| Final | 12/28/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/28/2020 | Approved | ENRIQUE MIRELES |
| MERV13>=Final | 12/28/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/28/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/28/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 1/4/2021 | Partial Approval | ENRIQUE MIRELES |
| Final | 3/3/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 3/3/2021 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 3/15/2021 | Corrections Issued | ENRIQUE MIRELES |