7706-7708 N DUCOR AVE 91304
Certificate Information: 7706-7708 N DUCOR AVE 91304
- Application / Permit
- 19014-20000-05972
- Plan Check / Job No.
- B19VN19062
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) IRR. 19'-4" X 23'-3" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ADD IRR. 11'-2" X 25'-11" TO EXTEND (E) LIVING ROOM, REMODEL BEDROOM AND ADD A 3/4 BATHROOM. ADD IRR. 6'-6" X 18'-6" FRONT PORCH. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | JENNIFER LEE |
| Corrections Issued | 11/6/2019 | JENNIFER LEE |
| Plan Check Approved | 11/21/2019 | ANGELICA MARTINEZ |
| Issued | 11/21/2019 | LADBS |
| CofO in Progress | 1/3/2021 | DAVID STEPANYAN |
| Permit Finaled | 1/6/2021 | JOHN JANSON |
| CofO Issued | 1/6/2021 | JOHN JANSON |
| Permit Finaled | 1/6/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/14/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 11/19/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 11/19/2019 | CELINA MORENO |
Contact Information
| Contractor | Flowers Construction; Lic. No.: 995868-B | 23055 SHERMAN WAY #5168 WEST HILLS, CA 91308 |
| Engineer | , ; Lic. No.: C88965 | 16526 BLACKHAWK ST. GRANADA HILLS, CA 91344 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2019 | Not Ready for Inspection | PETER FOLLING |
| Deputy Drilled-In Anchors | 12/18/2019 | No Access for Inspection | PETER FOLLING |
| PLUMBING-Rough | 12/23/2019 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 12/27/2019 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 12/27/2019 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/31/2019 | Partial Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 1/3/2020 | Not Ready for Inspection | PETER FOLLING |
| Underground Mechanical | 1/3/2020 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 1/7/2020 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 1/7/2020 | Partial Approval | PETER FOLLING |
| Sewer | 1/7/2020 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 1/14/2020 | Approved | PETER FOLLING |
| Gas Test | 1/16/2020 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 1/16/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Partial Approval | PETER FOLLING |
| Deputy Wood Construction | 2/19/2020 | No Access for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 2/25/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 2/25/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 2/25/2020 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 2/25/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 2/25/2020 | Approved | DAVID SANDOVAL |
| Insulation | 3/2/2020 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/2/2020 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 3/2/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 3/10/2020 | Corrections Issued | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/8/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Drywall Nailing | 12/7/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 12/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 12/7/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 12/7/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 12/7/2020 | Approved | DAVID STEPANYAN |
| Final | 12/31/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 12/31/2020 | Approved | DAVID STEPANYAN |
| Special/Order Compliance | 1/5/2021 | Corrections Issued | DAVID STEPANYAN |