22141 W COVELLO ST 91303
Certificate Information: 22141 W COVELLO ST 91303
- Application / Permit
- 19014-20000-05949
- Plan Check / Job No.
- B19VN18990
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Attach a 23' x 31'-6" Accessory Dwelling Unit per AB 494 & SB 229 to detached garage.
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofO Issued on 5/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2019 | ANGELICA DAVE |
| Corrections Issued | 11/1/2019 | ANGELICA DAVE |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Plan Check Approved | 2/27/2020 | ANGELICA MARTINEZ |
| Issued | 8/11/2020 | APPLICANT |
| CofO in Progress | 5/20/2021 | DAVID STEPANYAN |
| Permit Finaled | 5/27/2021 | MICHAEL SMITH |
| CofO Issued | 5/27/2021 | MICHAEL SMITH |
| Permit Finaled | 5/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 1/15/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | JOHN LIN |
| Sewer availability | Cleared | 2/11/2020 | JOHN LIN |
| Low Impact Development | Cleared | 2/19/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/26/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 10/7/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Special/Order Compliance | 10/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 10/29/2020 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/30/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/4/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/4/2020 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 12/4/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/16/2020 | Approved | DONALD SUNSERI |
| PLUMBING-Rough | 12/16/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 12/22/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 12/22/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 12/22/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/22/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 1/7/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 1/12/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 1/20/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 2/12/2021 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 2/12/2021 | Approved | DAVID STEPANYAN |
| Final | 4/1/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 4/1/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 4/1/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 5/19/2021 | Approved | DAVID STEPANYAN |
| Final | 5/19/2021 | OK to Issue CofO | DAVID STEPANYAN |
| HVAC-Final | 5/19/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 5/19/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2021 | SGSOV Approved | DAVID STEPANYAN |