4332 N WILKINSON AVE 91604

Certificate Information: 4332 N WILKINSON AVE 91604

Application / Permit
19014-20000-05940
Plan Check / Job No.
B19VN18963
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 298 SQ-FT of living area TO (E) SFD AND MAJOR REMODEL INTERIOR REMODEL
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 MOHAMMAD ESMAILI
Corrections Issued 12/4/2019 MOHAMMAD ESMAILI
Quality Review Completed 12/5/2019 OMID HEDAYAT
Building Plans Picked Up 12/5/2019 APPLICANT
Green Plans Picked Up 12/5/2019 APPLICANT
Applicant returned to address corrections 12/23/2019 MOHAMMAD ESMAILI
Plan Check Approved 1/10/2020 MOHAMMAD ESMAILI
Issued 1/24/2020 LADBS
CofO in Progress 5/5/2022 ARAM AVEDISIAN
Permit Finaled 8/6/2022 DEROLD HAUFF
CofO Issued 8/6/2022 DEROLD HAUFF
Permit Finaled 8/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/19/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/19/2019 ADRIAN CASTRO
ZI Cleared 12/19/2019 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 4/15/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 10/30/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/30/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 3/31/2021 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 4/14/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/14/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/14/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/14/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/20/2021 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 4/20/2021 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 4/20/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/20/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/7/2021 No Access for Inspection ARAM AVEDISIAN
HVAC-Rough 5/7/2021 No Access for Inspection ARAM AVEDISIAN
PLUMBING-Rough 5/7/2021 No Access for Inspection ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 5/11/2021 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/17/2021 Approved JOHN HAYES
Green Building Rough 5/17/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 5/17/2021 Approved JOHN HAYES
Special/Order Compliance 6/16/2021 Partial Inspection ARAM AVEDISIAN
Insulation 7/7/2021 Approved ARAM AVEDISIAN
Drywall Nailing 8/12/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/12/2021 Partial Approval ARAM AVEDISIAN
Shower Pan 8/12/2021 Approved ARAM AVEDISIAN
Special/Order Compliance 9/22/2021 Corrections Issued ARAM AVEDISIAN
Special/Order Compliance 10/27/2021 Partial Inspection ARAM AVEDISIAN
Special/Order Compliance 10/27/2021 Partial Inspection MICHAEL PELHAM
Final 4/21/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/21/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 4/21/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 5/2/2022 Corrections Issued MICHAEL TEMPLE
Smoke Detectors 5/2/2022 Approved MICHAEL TEMPLE
ELECTRICAL-Final 5/5/2022 Approved ARAM AVEDISIAN
Final 5/5/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 5/5/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 5/5/2022 Approved ARAM AVEDISIAN