6842 N BERTRAND AVE 91335

Certificate Information: 6842 N BERTRAND AVE 91335

Application / Permit
19014-20000-05918
Plan Check / Job No.
B19VN18898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADD 37'-0" X 25'-6" IRREG SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229 TO (E) DETACHED GARAGE
Permit Issued
Issued on 6/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2019 APPLICANT
Assigned to Plan Check Engineer 11/1/2019 JEROME MAGAT PALMA
Corrections Issued 11/4/2019 JEROME MAGAT PALMA
Building Plans Picked Up 11/4/2019 APPLICANT
Plan Check Approved 6/5/2020 JEROME MAGAT PALMA
Issued 6/19/2020 LADBS
CofO in Progress 10/23/2020 DAVID SCANTLIN
Permit Finaled 10/23/2020 JOHN JANSON
CofO Issued 10/23/2020 JOHN JANSON
Permit Finaled 10/23/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/20/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/20/2019 ADRIAN CASTRO
Sewer availability Cleared 11/20/2019 ADRIAN CASTRO
Construction near power lines Cleared 1/9/2020 RIDWAN HARDY
Low Impact Development Cleared 5/20/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/28/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Canby,, John Christopher; Lic. No.: C21514 2370 MIDLOTHIAN DRIVE      ALTADENA, CA 91001

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/24/2020 Partial Approval VINCENT HANLEY
Sewer 6/24/2020 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 6/25/2020 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/29/2020 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 7/22/2020 Approved VINCENT HANLEY
Deputy Wood Construction 7/22/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/30/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 7/30/2020 Approved VINCENT HANLEY
Green Building Rough 7/30/2020 Approved VINCENT HANLEY
HVAC-Rough 7/30/2020 Approved VINCENT HANLEY
PLUMBING-Rough 7/30/2020 Approved VINCENT HANLEY
Insulation 8/4/2020 Approved VINCENT HANLEY
Drywall Nailing 8/7/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/7/2020 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 8/14/2020 Approved VINCENT HANLEY
Shower Pan 8/14/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 9/14/2020 Approved VINCENT HANLEY
Final 9/14/2020 Corrections Issued VINCENT HANLEY
HVAC-Final 9/14/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Final 9/14/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 9/30/2020 Approved VINCENT HANLEY
Final 9/30/2020 Corrections Issued VINCENT HANLEY
Green Building Final 9/30/2020 Approved VINCENT HANLEY
HVAC-Final 9/30/2020 Approved VINCENT HANLEY
PLUMBING-Final 9/30/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/30/2020 Approved VINCENT HANLEY
Final 10/22/2020 OK to Issue CofO DAVID SCANTLIN