6842 N BERTRAND AVE 91335
Certificate Information: 6842 N BERTRAND AVE 91335
- Application / Permit
- 19014-20000-05918
- Plan Check / Job No.
- B19VN18898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADD 37'-0" X 25'-6" IRREG SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229 TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 11/4/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Plan Check Approved | 6/5/2020 | JEROME MAGAT PALMA |
| Issued | 6/19/2020 | LADBS |
| CofO in Progress | 10/23/2020 | DAVID SCANTLIN |
| Permit Finaled | 10/23/2020 | JOHN JANSON |
| CofO Issued | 10/23/2020 | JOHN JANSON |
| Permit Finaled | 10/23/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 1/9/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/20/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/28/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Canby,, John Christopher; Lic. No.: C21514 | 2370 MIDLOTHIAN DRIVE ALTADENA, CA 91001 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/24/2020 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/25/2020 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/29/2020 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 7/22/2020 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 7/22/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/30/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/30/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/30/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/30/2020 | Approved | VINCENT HANLEY |
| Insulation | 8/4/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 8/7/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/7/2020 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/14/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 8/14/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/14/2020 | Approved | VINCENT HANLEY |
| Final | 9/14/2020 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/14/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 9/14/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/30/2020 | Approved | VINCENT HANLEY |
| Final | 9/30/2020 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 9/30/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/30/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/30/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/30/2020 | Approved | VINCENT HANLEY |
| Final | 10/22/2020 | OK to Issue CofO | DAVID SCANTLIN |