7600-7602 N CORBIN AVE 91335

Certificate Information: 7600-7602 N CORBIN AVE 91335

Application / Permit
19014-20000-05902
Plan Check / Job No.
B19VN18846
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE THE ATTACHED CARPORT AND ADD 21'-0" X 25'-6" IRREGULAR SHAPE TWO STORY ATTACHED ACCESSORY DWELLING UNIT TO SFD PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/4/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 PARISA ZAHABI
Corrections Issued 11/27/2019 PARISA ZAHABI
Green Plans Picked Up 12/2/2019 APPLICANT
Quality Review Completed 12/11/2019 OMID HEDAYAT
Building Plans Picked Up 12/13/2019 APPLICANT
Applicant returned to address corrections 7/2/2020 PARISA ZAHABI
Plan Check Approved 7/29/2020 PARISA ZAHABI
Issued 8/4/2020 APPLICANT
CofO in Progress 4/7/2021 VINCENT HANLEY
Permit Finaled 4/12/2021 MICHAEL SMITH
CofO Issued 4/12/2021 MICHAEL SMITH
Permit Finaled 4/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/13/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/13/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 12/13/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 12/13/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/13/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 6/4/2020 MICHAEL AYERS

Contact Information

Contractor Kendex Inc; Lic. No.: 855775-B P O BOX 2020      WINNETKA, CA 91396
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/13/2020 Partial Approval VINCENT HANLEY
Sewer 8/13/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/28/2020 Approved VINCENT HANLEY
Underground Mechanical 8/28/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/5/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Approved VINCENT HANLEY
Green Building Rough 11/5/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 11/5/2020 Approved VINCENT HANLEY
Insulation 11/19/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/19/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 12/4/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 12/4/2020 Approved DAVID SANDOVAL
ELECTRICAL-Final 4/7/2021 Approved VINCENT HANLEY
Final 4/7/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 4/7/2021 Approved VINCENT HANLEY
HVAC-Final 4/7/2021 Approved VINCENT HANLEY
PLUMBING-Final 4/7/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/7/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/7/2021 Approved VINCENT HANLEY