10419 W MCBROOM ST 91040

Certificate Information: 10419 W MCBROOM ST 91040

Application / Permit
19014-20000-05887
Plan Check / Job No.
B19VN18759
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-0" X 48'-7" IRREG SHAPED ADDITION AND REMODEL THROUGHOUT (E) SINGLE FAMILY DWELLING W/ ATTACHED GARAGE. 4'-0" X 18'-3" ADDITION TO ENLARGE (E) GARAGE AND 6'-0" X 9'-0" COVERED PATIO ADDITION
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
Issued on 11/19/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 JEROME MAGAT PALMA
Corrections Issued 11/1/2019 JEROME MAGAT PALMA
Building Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 10/26/2020 JEROME MAGAT PALMA
Plan Check Approved 11/19/2020 JEROME MAGAT PALMA
Issued 11/19/2020 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/5/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 11/5/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/5/2019 LEE GUILBEAUX
Low Impact Development Cleared 11/14/2019 JORGE MEJIA LEMUS
Grading Pre-Inspection Cleared 11/18/2019 BARTON HOLMES
Roof/Waste drainage to street Cleared 11/18/2019 MARKOS PEREZ-BRAN
Private sewage disp. approval Cleared 12/6/2019 PATRICK MISCHLICH
Specific Plan Cleared 10/14/2020 MIGUEL GAMBOA
ZI Cleared 10/14/2020 MIGUEL GAMBOA
GPI Written Notices Cleared 11/19/2020 JEROME MAGAT PALMA

Contact Information

Architect Hanna,, Remon; Lic. No.: C36271 23610 NEWHALL AVENUE   APT 213    SANTA CLARITA, CA 91321
Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 6/3/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 9/30/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 12/1/2021 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 1/14/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 1/19/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 1/19/2022 Corrections Issued MICHEL ABAJAN
HVAC-Rough 3/7/2022 Partial Inspection DAVID MATSON
PLUMBING-Rough 3/7/2022 Approved DAVID MATSON
Wood Frame 3/7/2022 Partial Inspection DAVID MATSON
BUILDING-Rough-Frame 3/17/2022 Conditional Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 3/17/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 4/1/2022 No Access for Inspection MATTHEW NELSON
Insulation 4/5/2022 Approved WILLIAM WREN
Drywall Nailing 4/21/2022 Partial Approval ASHLEY THOMPSON
HVAC-Rough 4/21/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/21/2022 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 12/14/2022 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 12/19/2022 Approved DAVID ANDERSON
Shower Pan 12/19/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/31/2023 Approved DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 3/31/2023 Approved DAVID ANDERSON
Green Building Rough 3/31/2023 Approved DAVID ANDERSON