14929 W SYLVAN ST 91411

Certificate Information: 14929 W SYLVAN ST 91411

Application / Permit
19014-20000-05879
Plan Check / Job No.
B19VN18731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel kitchen, create laundry closet and add 3.75' x 10.25' attached pato cover and irregular shape 21' x 12.5' for new bathroom and living room expansion. All works are per design
Permit Issued
Issued on 11/13/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/29/2019 MARVEL DELACRUZ
Corrections Issued 10/29/2019 MARVEL DELACRUZ
Applicant returned to address corrections 10/31/2019 RAPHAEL ROSAS
Plan Check Approved 10/31/2019 ALDOUS CHIC
Issued 11/13/2019 LADBS
CofO in Progress 2/23/2021 CHRISTOPHE COCHRAN
Permit Finaled 5/15/2021 MICHAEL SMITH
CofO Issued 5/15/2021 MICHAEL SMITH
Permit Finaled 5/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/31/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 10/31/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 13719 OXNARD ST 101      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/3/2020 No Access for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval MISAEL ESPARZA
Wood Frame 5/11/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/21/2020 Approved MISAEL ESPARZA
HVAC-Rough 5/21/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 5/21/2020 Approved MISAEL ESPARZA
Wood Frame 5/21/2020 Approved MISAEL ESPARZA
Insulation 6/19/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/29/2020 Approved MISAEL ESPARZA
Shower Pan 6/29/2020 Approved MISAEL ESPARZA
Drywall Nailing 7/9/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 1/11/2021 Not Ready for Inspection JOHN HAYES
Final 1/11/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/11/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 1/11/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/11/2021 Not Ready for Inspection JOHN HAYES
Posting Pre-Inspection 1/11/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Not Ready JOHN HAYES
Shower Pan 1/11/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 1/11/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/23/2021 Approved CHRISTOPHE COCHRAN
Final 2/23/2021 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/23/2021 Approved CHRISTOPHE COCHRAN
Green Building Final 2/23/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/23/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 2/23/2021 Approved CHRISTOPHE COCHRAN