2015 W ADDISON WAY 90041

Certificate Information: 2015 W ADDISON WAY 90041

Application / Permit
19014-20000-05871
Plan Check / Job No.
B19VN18688
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 7'-8" x 18' TO AND CONVERT GARAGE TO ACCEESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 SELLA BENYAMIN
Corrections Issued 10/31/2019 SELLA BENYAMIN
Building Plans Picked Up 11/1/2019 APPLICANT
Applicant returned to address corrections 12/2/2019 SELLA BENYAMIN
Applicant returned to address corrections 4/6/2020 SELLA BENYAMIN
Applicant returned to address corrections 6/2/2020 SELLA BENYAMIN
Plan Check Approved 6/19/2020 SELLA BENYAMIN
Issued 9/23/2020 APPLICANT
CofO in Progress 9/2/2021 CRAIG VAUGHAN
Permit Finaled 9/3/2021 DEROLD HAUFF
CofO Issued 9/3/2021 DEROLD HAUFF
Permit Finaled 9/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 11/1/2019 APEKSHYA BAJRACHARYA
Grading Pre-Inspection Cleared 11/1/2019 BARTON HOLMES
Sewer availability Cleared 11/1/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 11/19/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 11/25/2019 LEE GUILBEAUX
GPI Written Notices Cleared 6/2/2020 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/15/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/22/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 11/9/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/16/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 12/16/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/16/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 12/16/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/24/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 12/24/2020 Approved CRAIG VAUGHAN
Insulation 1/5/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/5/2021 Partial Approval CRAIG VAUGHAN
Sewer 1/5/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 1/8/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 1/8/2021 Approved CRAIG VAUGHAN
Sewer 1/8/2021 Partial Approval CRAIG VAUGHAN
Shower Pan 1/8/2021 Approved CRAIG VAUGHAN
Drywall Nailing 1/19/2021 Conditional Approval HAMIK HARTOUNIAN
Final 3/24/2021 Corrections Issued HAMIK HARTOUNIAN
Final 8/19/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/19/2021 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/19/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 9/1/2021 Approved CRAIG VAUGHAN
Final 9/1/2021 OK to Issue CofO CRAIG VAUGHAN
Gas Test 9/1/2021 Approved CRAIG VAUGHAN
Green Building Final 9/1/2021 Approved CRAIG VAUGHAN
HVAC-Final 9/1/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 9/1/2021 Approved CRAIG VAUGHAN