7761-7763 N VARIEL AVE 91304

Certificate Information: 7761-7763 N VARIEL AVE 91304

Application / Permit
19014-20000-05840
Plan Check / Job No.
B19VN18548
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CREATE NEW BATHROOM WITHIN BEDROOM, CONVERT LAUNDRY ROOM TO BATHROOM AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 10/28/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2019 APPLICANT
Assigned to Plan Check Engineer 10/28/2019 ALDOUS CHIC
Corrections Issued 10/28/2019 ALDOUS CHIC
Plan Check Approved 10/28/2019 ARTIN ZARUKIAN
Issued 10/28/2019 LADBS
CofO in Progress 4/3/2020 HENRY KIM
CofO Issued 4/16/2020 DONALD SUNSERI
Permit Finaled 4/16/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 10/28/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/28/2019 GUILLERMO PETRA
Sewer availability Cleared 10/28/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2019 Not Ready for Inspection JOHN JANSON
Excavation/Setback/Form/Re-Bar 12/13/2019 Approved HENRY KIM
BUILDING-Rough-Frame 12/26/2019 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 12/26/2019 Not Ready for Inspection VINCENT HANLEY
Gas Test 12/26/2019 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 12/26/2019 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/26/2019 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 12/30/2019 Approved RONALD COWAN
Insulation 12/30/2019 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 12/30/2019 Approved RONALD COWAN
BUILDING-Rough-Frame 1/6/2020 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 1/6/2020 Approved DAVID SCANTLIN
Sewer 1/6/2020 Approved DAVID SCANTLIN
Wood Frame 1/9/2020 Corrections Issued HENRY KIM
HVAC-Rough 1/14/2020 Approved HENRY KIM
Wood Frame 1/14/2020 Approved HENRY KIM
Interior/Exterior Lathing 1/16/2020 Partial Approval PETER FOLLING
Insulation 1/17/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Approved HENRY KIM
Drywall Nailing 1/27/2020 Partial Approval HENRY KIM
Drywall Nailing 1/29/2020 Approved HENRY KIM
Gas Test 1/29/2020 Approved HENRY KIM
Shower Pan 1/31/2020 Partial Approval HENRY KIM
PLUMBING-Rough 3/2/2020 Approved HENRY KIM
Shower Pan 3/4/2020 Approved HENRY KIM
BUILDING-Rough-Frame 3/31/2020 Approved HENRY KIM
ELECTRICAL-Final 3/31/2020 Corrections Issued HENRY KIM
Final 3/31/2020 Corrections Issued HENRY KIM
Green Building Final 3/31/2020 Approved HENRY KIM
HVAC-Final 3/31/2020 Corrections Issued HENRY KIM
PLUMBING-Final 3/31/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/31/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 3/31/2020 Approved HENRY KIM
ELECTRICAL-Final 4/2/2020 Approved HENRY KIM
Final 4/2/2020 OK to Issue CofO HENRY KIM
HVAC-Final 4/2/2020 Approved HENRY KIM
PLUMBING-Final 4/2/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 4/2/2020 SGSOV Approved HENRY KIM
Service/Power Release 4/2/2020 Approved HENRY KIM